voestalpine Rail Technology GmbH
voestalpine Rail Technology GmbH is a production or processing of ferrous metals installation in Austria. In 2025 it reported 47,950 tonnes of verified emissions against 33,455 free allowances.
Key figures
Country
Installation ID
AT 201690
Verified emissions, 2025
47,950 tCO₂e
Free allocation, 2025
33,455 allowances
Allowance position, 2025
14,495 short
Compliance, 2024
A
Permit
IVA257
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 47,950 | 33,455 | 14,495 short |
| 2024 | 47,181 | 33,455 | 13,726 short |
| 2023 | 45,833 | 33,455 | 12,378 short |
| 2022 | 46,741 | 33,684 | 13,057 short |
| 2021 | 49,065 | 33,455 | 15,610 short |
| 2020 | 48,285 | 38,450 | 9,835 short |
| 2019 | 48,666 | 39,259 | 9,407 short |
| 2018 | 49,661 | 40,066 | 9,595 short |
| 2017 | 48,582 | 40,863 | 7,719 short |
| 2016 | 46,625 | 41,652 | 4,973 short |
| 2015 | 53,796 | 42,433 | 11,363 short |
| 2014 | 51,351 | 43,206 | 8,145 short |
| 2013 | 49,942 | 43,969 | 5,973 short |
Verified emissions changed by -4% from 2013 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
In 2025, verified emissions exceeded free allocation by 14,495 allowances, which the operator had to obtain.
Illustrative value at the latest reference price of €84.41 (30 September 2026): €1,223,523. Not the installation's actual cost, which depends on when and how it acquired allowances.
Price source: EU ETS primary auctions · latest price
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
CBAM context
This activity falls in the iron and steel sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.
| 2026 | 2027 | 2028 | 2029 | 2030 | 2031 | 2032 | 2033 | 2034 |
|---|---|---|---|---|---|---|---|---|
| 97.5% | 95% | 90% | 77.5% | 51.5% | 39% | 26.5% | 14% | 0% |
Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.
Proposed change
A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.
More on CBAM: the India CBAM Center and what CBAM is and how it works.
Nearby installations
Production or processing of ferrous metals installations in Austria, largest first.
- voestalpine Tubulars GmbH & Co KG 59,372 t in 2025
- voestalpine Wire Rod Austria GmbH 36,036 t in 2025
- voestalpine Böhler Aerospace 13,533 t in 2025
- voestalpine Böhler Bleche - Hönigsberg 9,264 t in 2025
Questions about voestalpine Rail Technology GmbH
How much did voestalpine Rail Technology GmbH emit in 2025?
47,950 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did voestalpine Rail Technology GmbH receive?
33,455 in 2025.
Did voestalpine Rail Technology GmbH surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.