voestalpine Stahl Donawitz GmbH

voestalpine Stahl Donawitz GmbH is a production of pig iron or steel installation in Austria. In 2025 it reported 2,788,988 tonnes of verified emissions against 2,085,730 free allowances.

Key figures

Country

Austria

Activity

Production of pig iron or steel

Installation ID

AT 13

Verified emissions, 2025

2,788,988 tCO₂e

Free allocation, 2025

2,085,730 allowances

Allowance position, 2025

703,258 short

Compliance, 2024

A

Permit

IVA065

Data as of

1 April 2026

Emissions and free allocation by year

Verified emissions Free allocation
Verified emissions and free allocation of voestalpine Stahl Donawitz GmbHVerified emissions and free allocation from 2013 to 2025.01.3M2.5M3.8M5M2013 verified emissions: 2,918,014 t2014 verified emissions: 2,808,536 t2015 verified emissions: 2,981,508 t2016 verified emissions: 2,772,530 t2017 verified emissions: 3,075,201 t2018 verified emissions: 2,923,552 t2019 verified emissions: 2,846,643 t2020 verified emissions: 2,251,948 t2021 verified emissions: 2,958,608 t2022 verified emissions: 2,784,609 t2023 verified emissions: 2,742,027 t2024 verified emissions: 2,623,231 t2025 verified emissions: 2,788,988 t2013 free allocation: 1,918,954 t2014 free allocation: 1,885,592 t2015 free allocation: 1,851,839 t2016 free allocation: 1,817,734 t2017 free allocation: 1,783,268 t2018 free allocation: 1,748,463 t2019 free allocation: 1,713,228 t2020 free allocation: 1,677,873 t2021 free allocation: 1,794,520 t2022 free allocation: 2,085,854 t2023 free allocation: 2,085,854 t2024 free allocation: 2,085,730 t2025 free allocation: 2,085,730 t2013201520172019202120232025
YearVerified emissions (t) Free allocationPosition
2025 2,788,988 2,085,730 703,258 short
2024 2,623,231 2,085,730 537,501 short
2023 2,742,027 2,085,854 656,173 short
2022 2,784,609 2,085,854 698,755 short
2021 2,958,608 1,794,520 1,164,088 short
2020 2,251,948 1,677,873 574,075 short
2019 2,846,643 1,713,228 1,133,415 short
2018 2,923,552 1,748,463 1,175,089 short
2017 3,075,201 1,783,268 1,291,933 short
2016 2,772,530 1,817,734 954,796 short
2015 2,981,508 1,851,839 1,129,669 short
2014 2,808,536 1,885,592 922,944 short
2013 2,918,014 1,918,954 999,060 short

Verified emissions changed by -4.4% from 2013 to 2025.

Source: European Commission, Union Registry · Data as of 1 April 2026

Allowance position

In 2025, verified emissions exceeded free allocation by 703,258 allowances, which the operator had to obtain.

Illustrative value at the latest reference price of €85.90 (28 September 2026): €60,409,862. Not the installation's actual cost, which depends on when and how it acquired allowances.

Price source: EU ETS primary auctions · latest price

Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.

CBAM context

This activity falls in the iron and steel sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.

Free allocation remaining for CBAM-covered products, by year
202620272028202920302031203220332034
97.5%95%90%77.5%51.5%39%26.5%14%0%

Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.

Proposed change

A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.

More on CBAM: the India CBAM Center and what CBAM is and how it works.

Nearby installations

Production of pig iron or steel installations in Austria, largest first.

Questions about voestalpine Stahl Donawitz GmbH

How much did voestalpine Stahl Donawitz GmbH emit in 2025?

2,788,988 tonnes of verified emissions, per EU Union Registry compliance data.

How many free allowances did voestalpine Stahl Donawitz GmbH receive?

2,085,730 in 2025.

Did voestalpine Stahl Donawitz GmbH surrender enough allowances?

Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.