Galva prépeint - Flémalle

Galva prépeint - Flémalle is a production or processing of ferrous metals installation in Belgium. In 2025 it reported 140 tonnes of verified emissions against 422 free allowances.

Key figures

Country

Belgium

Activity

Production or processing of ferrous metals

Installation ID

BE 115

Verified emissions, 2025

140 tCO₂e

Free allocation, 2025

422 allowances

Allowance position, 2025

282 surplus

Compliance, 2024

A

Permit

WAI085P043

Data as of

1 April 2026

Emissions and free allocation by year

Verified emissions Free allocation
Verified emissions and free allocation of Galva prépeint - FlémalleVerified emissions and free allocation from 2013 to 2025.012.5k25k37.5k50k2013 verified emissions: 23,721 t2014 verified emissions: 17,639 t2015 verified emissions: 19,925 t2016 verified emissions: 27,992 t2017 verified emissions: 30,399 t2018 verified emissions: 38,144 t2019 verified emissions: 45,677 t2020 verified emissions: 25,810 t2021 verified emissions: 15,133 t2022 verified emissions: 1,558 t2023 verified emissions: 188 t2024 verified emissions: 41 t2025 verified emissions: 140 t2013 free allocation: 41,929 t2014 free allocation: 41,201 t2015 free allocation: 22,830 t2016 free allocation: 22,410 t2017 free allocation: 38,968 t2018 free allocation: 38,207 t2019 free allocation: 37,438 t2020 free allocation: 36,666 t2021 free allocation: 26,878 t2022 free allocation: 15,465 t2023 free allocation: 6,288 t2024 free allocation: 646 t2025 free allocation: 422 t2013201520172019202120232025
YearVerified emissions (t) Free allocationPosition
2025 140 422 282 surplus
2024 41 646 605 surplus
2023 188 6,288 6,100 surplus
2022 1,558 15,465 13,907 surplus
2021 15,133 26,878 11,745 surplus
2020 25,810 36,666 10,856 surplus
2019 45,677 37,438 8,239 short
2018 38,144 38,207 63 surplus
2017 30,399 38,968 8,569 surplus
2016 27,992 22,410 5,582 short
2015 19,925 22,830 2,905 surplus
2014 17,639 41,201 23,562 surplus
2013 23,721 41,929 18,208 surplus

Verified emissions changed by -99.4% from 2013 to 2025.

Source: European Commission, Union Registry · Data as of 1 April 2026

Allowance position

Free allocation exceeded verified emissions in 2025, by 282 allowances.

Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.

CBAM context

This activity falls in the iron and steel sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.

Free allocation remaining for CBAM-covered products, by year
202620272028202920302031203220332034
97.5%95%90%77.5%51.5%39%26.5%14%0%

Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.

Proposed change

A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.

More on CBAM: the India CBAM Center and what CBAM is and how it works.

Nearby installations

Production or processing of ferrous metals installations in Belgium, largest first.

Questions about Galva prépeint - Flémalle

How much did Galva prépeint - Flémalle emit in 2025?

140 tonnes of verified emissions, per EU Union Registry compliance data.

How many free allowances did Galva prépeint - Flémalle receive?

422 in 2025.

Did Galva prépeint - Flémalle surrender enough allowances?

Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.