PROMET STEEL AD

PROMET STEEL AD is a production or processing of ferrous metals installation in Bulgaria. In 2025 it reported 36,556 tonnes of verified emissions against 29,412 free allowances.

Key figures

Country

Bulgaria

Activity

Production or processing of ferrous metals

Installation ID

BG 116

Verified emissions, 2025

36,556 tCO₂e

Free allocation, 2025

29,412 allowances

Allowance position, 2025

7,144 short

Compliance, 2024

A

Permit

BG-P116

Data as of

1 April 2026

Emissions and free allocation by year

Verified emissions Free allocation
Verified emissions and free allocation of PROMET STEEL ADVerified emissions and free allocation from 2013 to 2025.012.5k25k37.5k50k2013 verified emissions: 27,056 t2014 verified emissions: 24,656 t2015 verified emissions: 24,257 t2016 verified emissions: 29,776 t2017 verified emissions: 19,574 t2018 verified emissions: 33,502 t2019 verified emissions: 30,884 t2020 verified emissions: 34,772 t2021 verified emissions: 40,595 t2022 verified emissions: 31,790 t2023 verified emissions: 39,117 t2024 verified emissions: 37,712 t2025 verified emissions: 36,556 t2013 free allocation: 33,670 t2014 free allocation: 33,084 t2015 free allocation: 32,492 t2016 free allocation: 31,895 t2017 free allocation: 31,291 t2018 free allocation: 30,680 t2019 free allocation: 30,063 t2020 free allocation: 29,443 t2021 free allocation: 25,164 t2022 free allocation: 28,951 t2023 free allocation: 27,766 t2024 free allocation: 27,766 t2025 free allocation: 29,412 t2013201520172019202120232025
YearVerified emissions (t) Free allocationPosition
2025 36,556 29,412 7,144 short
2024 37,712 27,766 9,946 short
2023 39,117 27,766 11,351 short
2022 31,790 28,951 2,839 short
2021 40,595 25,164 15,431 short
2020 34,772 29,443 5,329 short
2019 30,884 30,063 821 short
2018 33,502 30,680 2,822 short
2017 19,574 31,291 11,717 surplus
2016 29,776 31,895 2,119 surplus
2015 24,257 32,492 8,235 surplus
2014 24,656 33,084 8,428 surplus
2013 27,056 33,670 6,614 surplus

Verified emissions changed by +35.1% from 2013 to 2025.

Source: European Commission, Union Registry · Data as of 1 April 2026

Allowance position

In 2025, verified emissions exceeded free allocation by 7,144 allowances, which the operator had to obtain.

Illustrative value at the latest reference price of €84.87 (29 September 2026): €606,311. Not the installation's actual cost, which depends on when and how it acquired allowances.

Price source: EU ETS primary auctions · latest price

Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.

CBAM context

This activity falls in the iron and steel sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.

Free allocation remaining for CBAM-covered products, by year
202620272028202920302031203220332034
97.5%95%90%77.5%51.5%39%26.5%14%0%

Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.

Proposed change

A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.

More on CBAM: the India CBAM Center and what CBAM is and how it works.

Questions about PROMET STEEL AD

How much did PROMET STEEL AD emit in 2025?

36,556 tonnes of verified emissions, per EU Union Registry compliance data.

How many free allowances did PROMET STEEL AD receive?

29,412 in 2025.

Did PROMET STEEL AD surrender enough allowances?

Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.