Aalborg Portland A/S
Aalborg Portland A/S is a production of cement clinker installation in Denmark. It last reported verified emissions for 2024: 1,436,067 tonnes.
Key figures
Country
Activity
Installation ID
DK 342
Verified emissions, 2024
1,436,067 tCO₂e
Free allocation, 2024
1,498,603 allowances
Allowance position, 2024
Not available
Compliance, 2024
A
Permit
TCO2-7
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | none | 1,290,874 | |
| 2024 | 1,436,067 | 1,498,603 | 62,536 surplus |
| 2023 | 1,704,342 | 1,675,181 | 29,161 short |
| 2022 | 1,979,482 | 1,797,705 | 181,777 short |
| 2021 | 2,248,048 | 1,663,537 | 584,511 short |
| 2020 | 2,339,867 | 1,793,211 | 546,656 short |
| 2019 | 2,189,152 | 1,836,497 | 352,655 short |
| 2018 | 2,190,706 | 1,879,891 | 310,815 short |
| 2017 | 2,277,214 | 1,923,034 | 354,180 short |
| 2016 | 2,054,900 | 1,966,040 | 88,860 short |
| 2015 | 1,780,564 | 2,008,872 | 228,308 surplus |
| 2014 | 1,718,011 | 2,051,548 | 333,537 surplus |
| 2013 | 1,647,199 | 2,094,007 | 446,808 surplus |
Verified emissions changed by -12.8% from 2013 to 2024.
Source: European Commission, Union Registry ยท Data as of 1 April 2026
Allowance position
No verified emissions were reported for 2025, so there is no position for the latest year.
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
CBAM context
This activity falls in the cement sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.
| 2026 | 2027 | 2028 | 2029 | 2030 | 2031 | 2032 | 2033 | 2034 |
|---|---|---|---|---|---|---|---|---|
| 97.5% | 95% | 90% | 77.5% | 51.5% | 39% | 26.5% | 14% | 0% |
Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.
Proposed change
A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.
More on CBAM: the India CBAM Center and what CBAM is and how it works.
Questions about Aalborg Portland A/S
How much did Aalborg Portland A/S emit in 2024?
1,436,067 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did Aalborg Portland A/S receive?
1,498,603 in 2024.
Did Aalborg Portland A/S surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.