ECL DUIN
ECL DUIN is a production of cement clinker installation in France. In 2025 it reported 44,677 tonnes of verified emissions against 32,431 free allowances.
Key figures
Country
Activity
Installation ID
FR 391
Verified emissions, 2025
44,677 tCO₂e
Free allocation, 2025
32,431 allowances
Allowance position, 2025
12,246 short
Compliance, 2024
A
Permit
06103219
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 44,677 | 32,431 | 12,246 short |
| 2024 | 42,454 | 36,663 | 5,791 short |
| 2023 | 47,768 | 35,142 | 12,626 short |
| 2022 | 53,690 | 35,142 | 18,548 short |
| 2021 | 41,298 | 44,879 | 3,581 surplus |
| 2020 | 56,172 | 65,713 | 9,541 surplus |
| 2019 | 57,787 | 67,097 | 9,310 surplus |
| 2018 | 59,361 | 68,476 | 9,115 surplus |
| 2017 | 63,263 | 69,837 | 6,574 surplus |
| 2016 | 54,165 | 71,186 | 17,021 surplus |
| 2015 | 60,634 | 72,520 | 11,886 surplus |
| 2014 | 56,316 | 73,841 | 17,525 surplus |
| 2013 | 60,698 | 75,146 | 14,448 surplus |
Verified emissions changed by -26.4% from 2013 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
In 2025, verified emissions exceeded free allocation by 12,246 allowances, which the operator had to obtain.
Illustrative value at the latest reference price of €85.90 (28 September 2026): €1,051,931. Not the installation's actual cost, which depends on when and how it acquired allowances.
Price source: EU ETS primary auctions · latest price
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
CBAM context
This activity falls in the cement sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.
| 2026 | 2027 | 2028 | 2029 | 2030 | 2031 | 2032 | 2033 | 2034 |
|---|---|---|---|---|---|---|---|---|
| 97.5% | 95% | 90% | 77.5% | 51.5% | 39% | 26.5% | 14% | 0% |
Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.
Proposed change
A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.
More on CBAM: the India CBAM Center and what CBAM is and how it works.
Nearby installations
Production of cement clinker installations in France, largest first.
- Heidelberg Materials France Ciments - Usine de Cou 722,343 t in 2025
- VICAT Usine de Montalieu 678,993 t in 2025
- CHAUX ET DOLOMIES DU BOULONNAIS 506,067 t in 2025
- Lafarge Ciments - Usine du Teil 494,861 t in 2025
- Heidelberg Materials France Ciments Usine d’Airvau 439,415 t in 2025
Questions about ECL DUIN
How much did ECL DUIN emit in 2025?
44,677 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did ECL DUIN receive?
32,431 in 2025.
Did ECL DUIN surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.