LA PERELLE

LA PERELLE is a production of cement clinker installation in France. In 2025 it reported 25,022 tonnes of verified emissions against 17,687 free allowances.

Key figures

Country

France

Activity

Production of cement clinker

Installation ID

FR 205775

Verified emissions, 2025

25,022 tCO₂e

Free allocation, 2025

17,687 allowances

Allowance position, 2025

7,335 short

Compliance, 2024

A

Permit

06103134

Data as of

1 April 2026

Emissions and free allocation by year

Verified emissions Free allocation
Verified emissions and free allocation of LA PERELLEVerified emissions and free allocation from 2013 to 2025.012.5k25k37.5k50k2013 verified emissions: 27,363 t2014 verified emissions: 23,039 t2015 verified emissions: 22,136 t2016 verified emissions: 19,459 t2017 verified emissions: 22,594 t2018 verified emissions: 22,317 t2019 verified emissions: 22,709 t2020 verified emissions: 24,876 t2021 verified emissions: 24,760 t2022 verified emissions: 23,572 t2023 verified emissions: 23,772 t2024 verified emissions: 23,541 t2025 verified emissions: 25,022 t2013 free allocation: 41,225 t2014 free allocation: 40,509 t2015 free allocation: 39,785 t2016 free allocation: 39,052 t2017 free allocation: 38,313 t2018 free allocation: 37,566 t2019 free allocation: 36,810 t2020 free allocation: 36,050 t2021 free allocation: 17,687 t2022 free allocation: 20,653 t2023 free allocation: 20,653 t2024 free allocation: 17,687 t2025 free allocation: 17,687 t2013201520172019202120232025
YearVerified emissions (t) Free allocationPosition
2025 25,022 17,687 7,335 short
2024 23,541 17,687 5,854 short
2023 23,772 20,653 3,119 short
2022 23,572 20,653 2,919 short
2021 24,760 17,687 7,073 short
2020 24,876 36,050 11,174 surplus
2019 22,709 36,810 14,101 surplus
2018 22,317 37,566 15,249 surplus
2017 22,594 38,313 15,719 surplus
2016 19,459 39,052 19,593 surplus
2015 22,136 39,785 17,649 surplus
2014 23,039 40,509 17,470 surplus
2013 27,363 41,225 13,862 surplus

Verified emissions changed by -8.6% from 2013 to 2025.

Source: European Commission, Union Registry · Data as of 1 April 2026

Allowance position

In 2025, verified emissions exceeded free allocation by 7,335 allowances, which the operator had to obtain.

Illustrative value at the latest reference price of €85.90 (28 September 2026): €630,077. Not the installation's actual cost, which depends on when and how it acquired allowances.

Price source: EU ETS primary auctions · latest price

Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.

CBAM context

This activity falls in the cement sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.

Free allocation remaining for CBAM-covered products, by year
202620272028202920302031203220332034
97.5%95%90%77.5%51.5%39%26.5%14%0%

Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.

Proposed change

A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.

More on CBAM: the India CBAM Center and what CBAM is and how it works.

Nearby installations

Production of cement clinker installations in France, largest first.

Questions about LA PERELLE

How much did LA PERELLE emit in 2025?

25,022 tonnes of verified emissions, per EU Union Registry compliance data.

How many free allowances did LA PERELLE receive?

17,687 in 2025.

Did LA PERELLE surrender enough allowances?

Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.