Cementeria di Isola delle Femmine

Cementeria di Isola delle Femmine is a production of cement clinker installation in Italy. In 2025 it reported 245,684 tonnes of verified emissions against 184,667 free allowances.

Key figures

Country

Italy

Activity

Production of cement clinker

Installation ID

IT 536

Verified emissions, 2025

245,684 tCO₂e

Free allocation, 2025

184,667 allowances

Allowance position, 2025

61,017 short

Compliance, 2024

A

Permit

IT-A-797

Data as of

1 April 2026

Emissions and free allocation by year

Verified emissions Free allocation
Verified emissions and free allocation of Cementeria di Isola delle FemmineVerified emissions and free allocation from 2013 to 2025.0125k250k375k500k2013 verified emissions: 384,276 t2014 verified emissions: 362,866 t2015 verified emissions: 313,827 t2016 verified emissions: 334,815 t2017 verified emissions: 257,426 t2018 verified emissions: 253,360 t2019 verified emissions: 257,527 t2020 verified emissions: 223,121 t2021 verified emissions: 291,904 t2022 verified emissions: 283,188 t2023 verified emissions: 263,673 t2024 verified emissions: 203,202 t2025 verified emissions: 245,684 t2013 free allocation: 408,764 t2014 free allocation: 401,664 t2015 free allocation: 394,481 t2016 free allocation: 387,222 t2017 free allocation: 379,887 t2018 free allocation: 372,479 t2019 free allocation: 364,978 t2020 free allocation: 357,452 t2021 free allocation: 190,939 t2022 free allocation: 204,747 t2023 free allocation: 245,368 t2024 free allocation: 245,368 t2025 free allocation: 184,667 t2013201520172019202120232025
YearVerified emissions (t) Free allocationPosition
2025 245,684 184,667 61,017 short
2024 203,202 245,368 42,166 surplus
2023 263,673 245,368 18,305 short
2022 283,188 204,747 78,441 short
2021 291,904 190,939 100,965 short
2020 223,121 357,452 134,331 surplus
2019 257,527 364,978 107,451 surplus
2018 253,360 372,479 119,119 surplus
2017 257,426 379,887 122,461 surplus
2016 334,815 387,222 52,407 surplus
2015 313,827 394,481 80,654 surplus
2014 362,866 401,664 38,798 surplus
2013 384,276 408,764 24,488 surplus

Verified emissions changed by -36.1% from 2013 to 2025.

Source: European Commission, Union Registry · Data as of 1 April 2026

Allowance position

In 2025, verified emissions exceeded free allocation by 61,017 allowances, which the operator had to obtain.

Illustrative value at the latest reference price of €85.90 (28 September 2026): €5,241,360. Not the installation's actual cost, which depends on when and how it acquired allowances.

Price source: EU ETS primary auctions · latest price

Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.

CBAM context

This activity falls in the cement sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.

Free allocation remaining for CBAM-covered products, by year
202620272028202920302031203220332034
97.5%95%90%77.5%51.5%39%26.5%14%0%

Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.

Proposed change

A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.

More on CBAM: the India CBAM Center and what CBAM is and how it works.

Nearby installations

Production of cement clinker installations in Italy, largest first.

Questions about Cementeria di Isola delle Femmine

How much did Cementeria di Isola delle Femmine emit in 2025?

245,684 tonnes of verified emissions, per EU Union Registry compliance data.

How many free allowances did Cementeria di Isola delle Femmine receive?

184,667 in 2025.

Did Cementeria di Isola delle Femmine surrender enough allowances?

Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.