Cementeria di Vernasca

Cementeria di Vernasca is a production of cement clinker installation in Italy. In 2025 it reported 448,573 tonnes of verified emissions against 412,435 free allowances.

Key figures

Country

Italy

Activity

Production of cement clinker

Installation ID

IT 315

Verified emissions, 2025

448,573 tCO₂e

Free allocation, 2025

412,435 allowances

Allowance position, 2025

36,138 short

Compliance, 2024

A

Permit

IT-A-395

Data as of

1 April 2026

Emissions and free allocation by year

Verified emissions Free allocation
Verified emissions and free allocation of Cementeria di VernascaVerified emissions and free allocation from 2013 to 2025.0250k500k750k1M2013 verified emissions: 424,289 t2014 verified emissions: 368,611 t2015 verified emissions: 394,274 t2016 verified emissions: 392,724 t2017 verified emissions: 426,984 t2018 verified emissions: 445,363 t2019 verified emissions: 504,924 t2020 verified emissions: 521,807 t2021 verified emissions: 587,138 t2022 verified emissions: 473,012 t2023 verified emissions: 488,155 t2024 verified emissions: 424,999 t2025 verified emissions: 448,573 t2013 free allocation: 597,818 t2014 free allocation: 587,434 t2015 free allocation: 576,929 t2016 free allocation: 566,314 t2017 free allocation: 555,584 t2018 free allocation: 544,750 t2019 free allocation: 533,781 t2020 free allocation: 522,774 t2021 free allocation: 445,738 t2022 free allocation: 479,976 t2023 free allocation: 457,950 t2024 free allocation: 412,435 t2025 free allocation: 412,435 t2013201520172019202120232025
YearVerified emissions (t) Free allocationPosition
2025 448,573 412,435 36,138 short
2024 424,999 412,435 12,564 short
2023 488,155 457,950 30,205 short
2022 473,012 479,976 6,964 surplus
2021 587,138 445,738 141,400 short
2020 521,807 522,774 967 surplus
2019 504,924 533,781 28,857 surplus
2018 445,363 544,750 99,387 surplus
2017 426,984 555,584 128,600 surplus
2016 392,724 566,314 173,590 surplus
2015 394,274 576,929 182,655 surplus
2014 368,611 587,434 218,823 surplus
2013 424,289 597,818 173,529 surplus

Verified emissions changed by +5.7% from 2013 to 2025.

Source: European Commission, Union Registry · Data as of 1 April 2026

Allowance position

In 2025, verified emissions exceeded free allocation by 36,138 allowances, which the operator had to obtain.

Illustrative value at the latest reference price of €85.90 (28 September 2026): €3,104,254. Not the installation's actual cost, which depends on when and how it acquired allowances.

Price source: EU ETS primary auctions · latest price

Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.

CBAM context

This activity falls in the cement sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.

Free allocation remaining for CBAM-covered products, by year
202620272028202920302031203220332034
97.5%95%90%77.5%51.5%39%26.5%14%0%

Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.

Proposed change

A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.

More on CBAM: the India CBAM Center and what CBAM is and how it works.

Nearby installations

Production of cement clinker installations in Italy, largest first.

Questions about Cementeria di Vernasca

How much did Cementeria di Vernasca emit in 2025?

448,573 tonnes of verified emissions, per EU Union Registry compliance data.

How many free allowances did Cementeria di Vernasca receive?

412,435 in 2025.

Did Cementeria di Vernasca surrender enough allowances?

Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.