RIVA Acciaio - Stabilimento di Lesegno
RIVA Acciaio - Stabilimento di Lesegno is a production of pig iron or steel installation in Italy. In 2025 it reported 40,704 tonnes of verified emissions against 32,214 free allowances.
Key figures
Country
Activity
Installation ID
IT 58
Verified emissions, 2025
40,704 tCO₂e
Free allocation, 2025
32,214 allowances
Allowance position, 2025
8,490 short
Compliance, 2024
A
Permit
IT-A-70
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 40,704 | 32,214 | 8,490 short |
| 2024 | 40,731 | 38,516 | 2,215 short |
| 2023 | 47,368 | 58,052 | 10,684 surplus |
| 2022 | 55,174 | 58,263 | 3,089 surplus |
| 2021 | 80,347 | 43,092 | 37,255 short |
| 2020 | 54,237 | 59,416 | 5,179 surplus |
| 2019 | 59,336 | 60,667 | 1,331 surplus |
| 2018 | 74,862 | 61,913 | 12,949 short |
| 2017 | 83,966 | 63,145 | 20,821 short |
| 2016 | 63,077 | 64,365 | 1,288 surplus |
| 2015 | 64,760 | 65,571 | 811 surplus |
| 2014 | 59,567 | 66,764 | 7,197 surplus |
| 2013 | 59,744 | 67,945 | 8,201 surplus |
Verified emissions changed by -31.9% from 2013 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
In 2025, verified emissions exceeded free allocation by 8,490 allowances, which the operator had to obtain.
Illustrative value at the latest reference price of €84.87 (29 September 2026): €720,546. Not the installation's actual cost, which depends on when and how it acquired allowances.
Price source: EU ETS primary auctions · latest price
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
CBAM context
This activity falls in the iron and steel sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.
| 2026 | 2027 | 2028 | 2029 | 2030 | 2031 | 2032 | 2033 | 2034 |
|---|---|---|---|---|---|---|---|---|
| 97.5% | 95% | 90% | 77.5% | 51.5% | 39% | 26.5% | 14% | 0% |
Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.
Proposed change
A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.
More on CBAM: the India CBAM Center and what CBAM is and how it works.
Nearby installations
Production of pig iron or steel installations in Italy, largest first.
- Stabilimento di Taranto 3,094,279 t in 2025
- Acciaieria Arvedi S.p.A. 468,090 t in 2025
- Dalmine S.p.A.-Stabilimento di Dalmine 385,589 t in 2025
- Sito produttivo di Terni 340,059 t in 2025
- Acciaierie Bertoli Safau S.p.A. 236,422 t in 2025
Questions about RIVA Acciaio - Stabilimento di Lesegno
How much did RIVA Acciaio - Stabilimento di Lesegno emit in 2025?
40,704 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did RIVA Acciaio - Stabilimento di Lesegno receive?
32,214 in 2025.
Did RIVA Acciaio - Stabilimento di Lesegno surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.