AM Rodange et Schifflange - Site de Rodange

AM Rodange et Schifflange - Site de Rodange is a production or processing of ferrous metals installation in Luxembourg. It last reported verified emissions for 2024: 16,493 tonnes.

Key figures

Country

Luxembourg

Activity

Production or processing of ferrous metals

Installation ID

LU 205713

Verified emissions, 2024

16,493 tCO₂e

Free allocation, 2024

15,085 allowances

Allowance position, 2024

Not available

Compliance, 2024

A

Permit

EQE-2013-21

Data as of

1 April 2026

Emissions and free allocation by year

Verified emissions Free allocation
Verified emissions and free allocation of AM Rodange et Schifflange - Site de RodangeVerified emissions and free allocation from 2013 to 2025.012.5k25k37.5k50k2013 verified emissions: 18,951 t2014 verified emissions: 20,490 t2015 verified emissions: 19,758 t2016 verified emissions: 19,699 t2017 verified emissions: 20,389 t2018 verified emissions: 22,515 t2019 verified emissions: 16,982 t2020 verified emissions: 16,664 t2021 verified emissions: 19,307 t2022 verified emissions: 17,963 t2023 verified emissions: 17,845 t2024 verified emissions: 16,493 t2013 free allocation: 27,321 t2014 free allocation: 26,846 t2015 free allocation: 26,366 t2016 free allocation: 25,881 t2017 free allocation: 25,391 t2018 free allocation: 24,896 t2019 free allocation: 18,172 t2020 free allocation: 17,797 t2021 free allocation: 12,538 t2022 free allocation: 15,085 t2023 free allocation: 15,085 t2024 free allocation: 15,085 t2025 free allocation: 12,740 t2013201520172019202120232025
YearVerified emissions (t) Free allocationPosition
2025 none 12,740
2024 16,493 15,085 1,408 short
2023 17,845 15,085 2,760 short
2022 17,963 15,085 2,878 short
2021 19,307 12,538 6,769 short
2020 16,664 17,797 1,133 surplus
2019 16,982 18,172 1,190 surplus
2018 22,515 24,896 2,381 surplus
2017 20,389 25,391 5,002 surplus
2016 19,699 25,881 6,182 surplus
2015 19,758 26,366 6,608 surplus
2014 20,490 26,846 6,356 surplus
2013 18,951 27,321 8,370 surplus

Verified emissions changed by -13% from 2013 to 2024.

Source: European Commission, Union Registry ยท Data as of 1 April 2026

Allowance position

No verified emissions were reported for 2025, so there is no position for the latest year.

Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.

CBAM context

This activity falls in the iron and steel sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.

Free allocation remaining for CBAM-covered products, by year
202620272028202920302031203220332034
97.5%95%90%77.5%51.5%39%26.5%14%0%

Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.

Proposed change

A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.

More on CBAM: the India CBAM Center and what CBAM is and how it works.

Questions about AM Rodange et Schifflange - Site de Rodange

How much did AM Rodange et Schifflange - Site de Rodange emit in 2024?

16,493 tonnes of verified emissions, per EU Union Registry compliance data.

How many free allowances did AM Rodange et Schifflange - Site de Rodange receive?

15,085 in 2024.

Did AM Rodange et Schifflange - Site de Rodange surrender enough allowances?

Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.