ARCELORMITTAL HUNEDOARA SA
ARCELORMITTAL HUNEDOARA SA is a production of pig iron or steel installation in Romania. In 2025 it reported 17,993 tonnes of verified emissions against 29,402 free allowances.
Key figures
Country
Activity
Installation ID
RO 45
Verified emissions, 2025
17,993 tCO₂e
Free allocation, 2025
29,402 allowances
Allowance position, 2025
11,409 surplus
Compliance, 2024
A
Permit
103
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 17,993 | 29,402 | 11,409 surplus |
| 2024 | 38,518 | 27,044 | 11,474 short |
| 2023 | 43,047 | 27,985 | 15,062 short |
| 2022 | 31,917 | 33,566 | 1,649 surplus |
| 2021 | 48,709 | 33,566 | 15,143 short |
| 2020 | 41,977 | 55,759 | 13,782 surplus |
| 2019 | 45,314 | 56,933 | 11,619 surplus |
| 2018 | 52,376 | 58,102 | 5,726 surplus |
| 2017 | 56,706 | 59,258 | 2,552 surplus |
| 2016 | 53,448 | 60,403 | 6,955 surplus |
| 2015 | 50,533 | 61,535 | 11,002 surplus |
| 2014 | 51,549 | 40,981 | 10,568 short |
| 2013 | 43,808 | 41,705 | 2,103 short |
Verified emissions changed by -58.9% from 2013 to 2025.
Source: European Commission, Union Registry ยท Data as of 1 April 2026
Allowance position
Free allocation exceeded verified emissions in 2025, by 11,409 allowances.
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
CBAM context
This activity falls in the iron and steel sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.
| 2026 | 2027 | 2028 | 2029 | 2030 | 2031 | 2032 | 2033 | 2034 |
|---|---|---|---|---|---|---|---|---|
| 97.5% | 95% | 90% | 77.5% | 51.5% | 39% | 26.5% | 14% | 0% |
Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.
Proposed change
A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.
More on CBAM: the India CBAM Center and what CBAM is and how it works.
Nearby installations
Production of pig iron or steel installations in Romania, largest first.
- SC SILCOTUB SA Pct de lucru Calarasi 42,609 t in 2025
- ARTROM STEEL TUBES SA -Punct lucru Resita 20,968 t in 2025
- SC SATURN SA 1,348 t in 2025
Questions about ARCELORMITTAL HUNEDOARA SA
How much did ARCELORMITTAL HUNEDOARA SA emit in 2025?
17,993 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did ARCELORMITTAL HUNEDOARA SA receive?
29,402 in 2025.
Did ARCELORMITTAL HUNEDOARA SA surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.