Celsa Atlantic, S.L. - División Largos

Celsa Atlantic, S.L. - División Largos is a production or processing of ferrous metals installation in Spain. In 2025 it reported 18,497 tonnes of verified emissions against 15,940 free allowances.

Key figures

Country

Spain

Activity

Production or processing of ferrous metals

Installation ID

ES 205190

Verified emissions, 2025

18,497 tCO₂e

Free allocation, 2025

15,940 allowances

Allowance position, 2025

2,557 short

Compliance, 2024

A

Permit

ES12150610-649

Data as of

1 April 2026

Emissions and free allocation by year

Verified emissions Free allocation
Verified emissions and free allocation of Celsa Atlantic, S.L. - División LargosVerified emissions and free allocation from 2013 to 2025.012.5k25k37.5k50k2013 verified emissions: 40,245 t2014 verified emissions: 40,664 t2015 verified emissions: 31,606 t2016 verified emissions: 32,405 t2017 verified emissions: 31,264 t2018 verified emissions: 32,861 t2019 verified emissions: 31,253 t2020 verified emissions: 30,285 t2021 verified emissions: 31,514 t2022 verified emissions: 25,960 t2023 verified emissions: 22,456 t2024 verified emissions: 19,522 t2025 verified emissions: 18,497 t2013 free allocation: 47,665 t2014 free allocation: 46,837 t2015 free allocation: 45,999 t2016 free allocation: 45,153 t2017 free allocation: 44,298 t2018 free allocation: 43,434 t2019 free allocation: 42,559 t2020 free allocation: 41,682 t2021 free allocation: 25,623 t2022 free allocation: 25,623 t2023 free allocation: 25,623 t2024 free allocation: 18,379 t2025 free allocation: 15,940 t2013201520172019202120232025
YearVerified emissions (t) Free allocationPosition
2025 18,497 15,940 2,557 short
2024 19,522 18,379 1,143 short
2023 22,456 25,623 3,167 surplus
2022 25,960 25,623 337 short
2021 31,514 25,623 5,891 short
2020 30,285 41,682 11,397 surplus
2019 31,253 42,559 11,306 surplus
2018 32,861 43,434 10,573 surplus
2017 31,264 44,298 13,034 surplus
2016 32,405 45,153 12,748 surplus
2015 31,606 45,999 14,393 surplus
2014 40,664 46,837 6,173 surplus
2013 40,245 47,665 7,420 surplus

Verified emissions changed by -54% from 2013 to 2025.

Source: European Commission, Union Registry · Data as of 1 April 2026

Allowance position

In 2025, verified emissions exceeded free allocation by 2,557 allowances, which the operator had to obtain.

Illustrative value at the latest reference price of €84.87 (29 September 2026): €217,013. Not the installation's actual cost, which depends on when and how it acquired allowances.

Price source: EU ETS primary auctions · latest price

Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.

CBAM context

This activity falls in the iron and steel sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.

Free allocation remaining for CBAM-covered products, by year
202620272028202920302031203220332034
97.5%95%90%77.5%51.5%39%26.5%14%0%

Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.

Proposed change

A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.

More on CBAM: the India CBAM Center and what CBAM is and how it works.

Nearby installations

Production or processing of ferrous metals installations in Spain, largest first.

Questions about Celsa Atlantic, S.L. - División Largos

How much did Celsa Atlantic, S.L. - División Largos emit in 2025?

18,497 tonnes of verified emissions, per EU Union Registry compliance data.

How many free allowances did Celsa Atlantic, S.L. - División Largos receive?

15,940 in 2025.

Did Celsa Atlantic, S.L. - División Largos surrender enough allowances?

Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.