Galmed Steel, S.A. is a production or processing of ferrous metals installation in Spain. In 2025 it reported 7,798 tonnes of verified emissions against 12,397 free allowances.

Key figures

Country

Spain

Activity

Production or processing of ferrous metals

Installation ID

ES 208983

Verified emissions, 2025

7,798 tCO₂e

Free allocation, 2025

12,397 allowances

Allowance position, 2025

4,599 surplus

Compliance, 2024

A

Permit

ES10460616-44869

Data as of

1 April 2026

Emissions and free allocation by year

Verified emissions Free allocation
Verified emissions and free allocation of Galmed Steel, S.A.Verified emissions and free allocation from 2016 to 2025.012.5k25k37.5k50k2016 verified emissions: 882 t2017 verified emissions: 24,421 t2018 verified emissions: 24,227 t2019 verified emissions: 25,136 t2020 verified emissions: 16,838 t2021 verified emissions: 19,599 t2022 verified emissions: 19,749 t2023 verified emissions: 20,881 t2024 verified emissions: 15,418 t2025 verified emissions: 7,798 t2016 free allocation: 0 t2017 free allocation: 23,308 t2018 free allocation: 23,457 t2019 free allocation: 23,011 t2020 free allocation: 22,563 t2021 free allocation: 15,723 t2022 free allocation: 12,397 t2023 free allocation: 14,915 t2024 free allocation: 14,915 t2025 free allocation: 12,397 t2016201720182019202020212022202320242025
YearVerified emissions (t) Free allocationPosition
2025 7,798 12,397 4,599 surplus
2024 15,418 14,915 503 short
2023 20,881 14,915 5,966 short
2022 19,749 12,397 7,352 short
2021 19,599 15,723 3,876 short
2020 16,838 22,563 5,725 surplus
2019 25,136 23,011 2,125 short
2018 24,227 23,457 770 short
2017 24,421 23,308 1,113 short
2016 882 0 882 short

Verified emissions changed by +784.1% from 2016 to 2025.

Source: European Commission, Union Registry · Data as of 1 April 2026

Allowance position

Free allocation exceeded verified emissions in 2025, by 4,599 allowances.

Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.

CBAM context

This activity falls in the iron and steel sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.

Free allocation remaining for CBAM-covered products, by year
202620272028202920302031203220332034
97.5%95%90%77.5%51.5%39%26.5%14%0%

Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.

Proposed change

A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.

More on CBAM: the India CBAM Center and what CBAM is and how it works.

Nearby installations

Production or processing of ferrous metals installations in Spain, largest first.

Questions about Galmed Steel, S.A.

How much did Galmed Steel, S.A. emit in 2025?

7,798 tonnes of verified emissions, per EU Union Registry compliance data.

How many free allowances did Galmed Steel, S.A. receive?

12,397 in 2025.

Did Galmed Steel, S.A. surrender enough allowances?

Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.