Votorantim Cementos España, S.A. Fábrica de Niebla
Votorantim Cementos España, S.A. Fábrica de Niebla is a production of cement clinker installation in Spain. In 2025 it reported 238,032 tonnes of verified emissions against 318,646 free allowances.
Key figures
Country
Activity
Installation ID
ES 13
Verified emissions, 2025
238,032 tCO₂e
Free allocation, 2025
318,646 allowances
Allowance position, 2025
80,614 surplus
Compliance, 2024
A
Permit
ES012106000013
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 238,032 | 318,646 | 80,614 surplus |
| 2024 | 256,151 | 318,646 | 62,495 surplus |
| 2023 | 273,434 | 318,646 | 45,212 surplus |
| 2022 | 257,383 | 318,646 | 61,263 surplus |
| 2021 | 299,537 | 318,646 | 19,109 surplus |
| 2020 | 289,836 | 302,386 | 12,550 surplus |
| 2019 | 339,938 | 308,753 | 31,185 short |
| 2018 | 390,739 | 315,097 | 75,642 short |
| 2017 | 364,596 | 321,364 | 43,232 short |
| 2016 | 418,138 | 327,570 | 90,568 short |
| 2015 | 382,171 | 333,710 | 48,461 short |
| 2014 | 394,813 | 339,787 | 55,026 short |
| 2013 | 384,413 | 345,793 | 38,620 short |
Verified emissions changed by -38.1% from 2013 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
Free allocation exceeded verified emissions in 2025, by 80,614 allowances.
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
CBAM context
This activity falls in the cement sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.
| 2026 | 2027 | 2028 | 2029 | 2030 | 2031 | 2032 | 2033 | 2034 |
|---|---|---|---|---|---|---|---|---|
| 97.5% | 95% | 90% | 77.5% | 51.5% | 39% | 26.5% | 14% | 0% |
Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.
Proposed change
A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.
More on CBAM: the India CBAM Center and what CBAM is and how it works.
Nearby installations
Production of cement clinker installations in Spain, largest first.
- Cementos Molins Industrial S.A. 735,662 t in 2025
- Cementos Portland Valderrivas, S.A. 676,598 t in 2025
- LafargeHolcim España SAU Instalación de Carboneras 671,019 t in 2025
- Cementos Portland Valderrivas - Alcalá de Guadaira 640,047 t in 2025
- Cementos Portland Valderrivas - Morata de Tajuña 620,313 t in 2025
Questions about Votorantim Cementos España, S.A. Fábrica de Niebla
How much did Votorantim Cementos España, S.A. Fábrica de Niebla emit in 2025?
238,032 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did Votorantim Cementos España, S.A. Fábrica de Niebla receive?
318,646 in 2025.
Did Votorantim Cementos España, S.A. Fábrica de Niebla surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.