Votorantim Cementos España, S.A.-Fca. Málaga
Votorantim Cementos España, S.A.-Fca. Málaga is a production of cement clinker installation in Spain. In 2025 it reported 498,564 tonnes of verified emissions against 671,439 free allowances.
Key figures
Country
Activity
Installation ID
ES 14
Verified emissions, 2025
498,564 tCO₂e
Free allocation, 2025
671,439 allowances
Allowance position, 2025
172,875 surplus
Compliance, 2024
A
Permit
ES012906000014
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 498,564 | 671,439 | 172,875 surplus |
| 2024 | 542,890 | 671,439 | 128,549 surplus |
| 2023 | 599,491 | 671,439 | 71,948 surplus |
| 2022 | 549,142 | 671,439 | 122,297 surplus |
| 2021 | 629,365 | 671,439 | 42,074 surplus |
| 2020 | 628,521 | 543,266 | 85,255 short |
| 2019 | 603,887 | 554,705 | 49,182 short |
| 2018 | 807,987 | 566,104 | 241,883 short |
| 2017 | 809,373 | 577,362 | 232,011 short |
| 2016 | 829,728 | 588,512 | 241,216 short |
| 2015 | 690,188 | 599,544 | 90,644 short |
| 2014 | 711,875 | 610,461 | 101,414 short |
| 2013 | 574,391 | 621,252 | 46,861 surplus |
Verified emissions changed by -13.2% from 2013 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
Free allocation exceeded verified emissions in 2025, by 172,875 allowances.
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
CBAM context
This activity falls in the cement sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.
| 2026 | 2027 | 2028 | 2029 | 2030 | 2031 | 2032 | 2033 | 2034 |
|---|---|---|---|---|---|---|---|---|
| 97.5% | 95% | 90% | 77.5% | 51.5% | 39% | 26.5% | 14% | 0% |
Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.
Proposed change
A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.
More on CBAM: the India CBAM Center and what CBAM is and how it works.
Nearby installations
Production of cement clinker installations in Spain, largest first.
- Cementos Molins Industrial S.A. 735,662 t in 2025
- Cementos Portland Valderrivas, S.A. 676,598 t in 2025
- LafargeHolcim España SAU Instalación de Carboneras 671,019 t in 2025
- Cementos Portland Valderrivas - Alcalá de Guadaira 640,047 t in 2025
- Cementos Portland Valderrivas - Morata de Tajuña 620,313 t in 2025
Questions about Votorantim Cementos España, S.A.-Fca. Málaga
How much did Votorantim Cementos España, S.A.-Fca. Málaga emit in 2025?
498,564 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did Votorantim Cementos España, S.A.-Fca. Málaga receive?
671,439 in 2025.
Did Votorantim Cementos España, S.A.-Fca. Málaga surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.