Halmstadsverken

Halmstadsverken is a production of pig iron or steel installation in Sweden. In 2025 it reported 15,290 tonnes of verified emissions against 12,627 free allowances.

Key figures

Country

Sweden

Activity

Production of pig iron or steel

Installation ID

SE 488

Verified emissions, 2025

15,290 tCO₂e

Free allocation, 2025

12,627 allowances

Allowance position, 2025

2,663 short

Compliance, 2024

A

Permit

13-563-010858-2004

Data as of

1 April 2026

Emissions and free allocation by year

Verified emissions Free allocation
Verified emissions and free allocation of HalmstadsverkenVerified emissions and free allocation from 2013 to 2025.012.5k25k37.5k50k2013 verified emissions: 21,156 t2014 verified emissions: 24,609 t2015 verified emissions: 22,688 t2016 verified emissions: 23,512 t2017 verified emissions: 25,540 t2018 verified emissions: 24,809 t2019 verified emissions: 19,921 t2020 verified emissions: 19,910 t2021 verified emissions: 25,385 t2022 verified emissions: 17,960 t2023 verified emissions: 12,761 t2024 verified emissions: 14,085 t2025 verified emissions: 15,290 t2013 free allocation: 16,222 t2014 free allocation: 15,940 t2015 free allocation: 15,656 t2016 free allocation: 15,368 t2017 free allocation: 15,077 t2018 free allocation: 14,782 t2019 free allocation: 14,485 t2020 free allocation: 14,186 t2021 free allocation: 11,656 t2022 free allocation: 16,667 t2023 free allocation: 16,532 t2024 free allocation: 13,295 t2025 free allocation: 12,627 t2013201520172019202120232025
YearVerified emissions (t) Free allocationPosition
2025 15,290 12,627 2,663 short
2024 14,085 13,295 790 short
2023 12,761 16,532 3,771 surplus
2022 17,960 16,667 1,293 short
2021 25,385 11,656 13,729 short
2020 19,910 14,186 5,724 short
2019 19,921 14,485 5,436 short
2018 24,809 14,782 10,027 short
2017 25,540 15,077 10,463 short
2016 23,512 15,368 8,144 short
2015 22,688 15,656 7,032 short
2014 24,609 15,940 8,669 short
2013 21,156 16,222 4,934 short

Verified emissions changed by -27.7% from 2013 to 2025.

Source: European Commission, Union Registry · Data as of 1 April 2026

Allowance position

In 2025, verified emissions exceeded free allocation by 2,663 allowances, which the operator had to obtain.

Illustrative value at the latest reference price of €84.87 (29 September 2026): €226,009. Not the installation's actual cost, which depends on when and how it acquired allowances.

Price source: EU ETS primary auctions · latest price

Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.

CBAM context

This activity falls in the iron and steel sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.

Free allocation remaining for CBAM-covered products, by year
202620272028202920302031203220332034
97.5%95%90%77.5%51.5%39%26.5%14%0%

Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.

Proposed change

A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.

More on CBAM: the India CBAM Center and what CBAM is and how it works.

Nearby installations

Production of pig iron or steel installations in Sweden, largest first.

Questions about Halmstadsverken

How much did Halmstadsverken emit in 2025?

15,290 tonnes of verified emissions, per EU Union Registry compliance data.

How many free allowances did Halmstadsverken receive?

12,627 in 2025.

Did Halmstadsverken surrender enough allowances?

Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.