Anlage zum Brennen von Ölschiefer - Blöcke 1bis 4
Anlage zum Brennen von Ölschiefer - Blöcke 1bis 4 is a production of cement clinker installation in Germany. In 2025 it reported 165,954 tonnes of verified emissions against 163,208 free allowances.
Key figures
Country
Activity
Installation ID
DE 113
Verified emissions, 2025
165,954 tCO₂e
Free allocation, 2025
163,208 allowances
Allowance position, 2025
2,746 short
Compliance, 2024
A
Permit
14230-0042
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 165,954 | 163,208 | 2,746 short |
| 2024 | 171,434 | 195,380 | 23,946 surplus |
| 2023 | 170,430 | 195,380 | 24,950 surplus |
| 2022 | 179,091 | 195,380 | 16,289 surplus |
| 2021 | 174,930 | 195,380 | 20,450 surplus |
| 2020 | 190,120 | 129,976 | 60,144 short |
| 2019 | 201,183 | 132,677 | 68,506 short |
| 2018 | 207,622 | 135,371 | 72,251 short |
| 2017 | 208,115 | 138,039 | 70,076 short |
| 2016 | 202,021 | 140,686 | 61,335 short |
| 2015 | 193,488 | 143,311 | 50,177 short |
| 2014 | 205,457 | 145,915 | 59,542 short |
| 2013 | 192,883 | 148,495 | 44,388 short |
Verified emissions changed by -14% from 2013 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
In 2025, verified emissions exceeded free allocation by 2,746 allowances, which the operator had to obtain.
Illustrative value at the latest reference price of €85.90 (28 September 2026): €235,881. Not the installation's actual cost, which depends on when and how it acquired allowances.
Price source: EU ETS primary auctions · latest price
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
CBAM context
This activity falls in the cement sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.
| 2026 | 2027 | 2028 | 2029 | 2030 | 2031 | 2032 | 2033 | 2034 |
|---|---|---|---|---|---|---|---|---|
| 97.5% | 95% | 90% | 77.5% | 51.5% | 39% | 26.5% | 14% | 0% |
Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.
Proposed change
A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.
More on CBAM: the India CBAM Center and what CBAM is and how it works.
Nearby installations
Production of cement clinker installations in Germany, largest first.
- Werk Lägerdorf 816,206 t in 2025
- Zementwerk Burglengenfeld 786,942 t in 2025
- Zementwerk Rüdersdorf 784,737 t in 2025
- Zementwerk Karsdorf 757,120 t in 2025
- Drehöfen Deuna 689,842 t in 2025
Questions about Anlage zum Brennen von Ölschiefer - Blöcke 1bis 4
How much did Anlage zum Brennen von Ölschiefer - Blöcke 1bis 4 emit in 2025?
165,954 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did Anlage zum Brennen von Ölschiefer - Blöcke 1bis 4 receive?
163,208 in 2025.
Did Anlage zum Brennen von Ölschiefer - Blöcke 1bis 4 surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.