Produktion Ettringen
Produktion Ettringen is a production of paper or cardboard installation in Germany. In 2025 it reported 16,267 tonnes of verified emissions against 46,337 free allowances.
Key figures
Country
Activity
Installation ID
DE 610
Verified emissions, 2025
16,267 tCO₂e
Free allocation, 2025
46,337 allowances
Allowance position, 2025
30,070 surplus
Compliance, 2024
A
Permit
14280-0129
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 16,267 | 46,337 | 30,070 surplus |
| 2024 | 62,613 | 46,337 | 16,276 short |
| 2023 | 55,022 | 64,392 | 9,370 surplus |
| 2022 | 69,780 | 74,234 | 4,454 surplus |
| 2021 | 93,334 | 74,234 | 19,100 short |
| 2020 | 92,806 | 60,787 | 32,019 short |
| 2019 | 100,165 | 62,066 | 38,099 short |
| 2018 | 97,965 | 63,343 | 34,622 short |
| 2017 | 98,329 | 64,602 | 33,727 short |
| 2016 | 97,243 | 65,849 | 31,394 short |
| 2015 | 73,282 | 67,084 | 6,198 short |
| 2014 | 56,138 | 108,933 | 52,795 surplus |
| 2013 | 62,735 | 110,858 | 48,123 surplus |
Verified emissions changed by -74.1% from 2013 to 2025.
Source: European Commission, Union Registry ยท Data as of 1 April 2026
Allowance position
Free allocation exceeded verified emissions in 2025, by 30,070 allowances.
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
Nearby installations
Production of paper or cardboard installations in Germany, largest first.
- PKVarel Papierfabrik 272,732 t in 2025
- R-Zeitungsdruckpapierfabrik 187,336 t in 2025
- KM III 173,266 t in 2025
- Anlage zur Papierherstellung 168,114 t in 2025
- Heizkraftwerk der PF Adolf Jass 149,098 t in 2025
Questions about Produktion Ettringen
How much did Produktion Ettringen emit in 2025?
16,267 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did Produktion Ettringen receive?
46,337 in 2025.
Did Produktion Ettringen surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.