Roheisenerzeugung Dillingen
Roheisenerzeugung Dillingen is a production of pig iron or steel installation in Germany. In 2025 it reported 3,646,506 tonnes of verified emissions against 6,267,829 free allowances.
Key figures
Country
Activity
Installation ID
DE 52
Verified emissions, 2025
3,646,506 tCO₂e
Free allocation, 2025
6,267,829 allowances
Allowance position, 2025
2,621,323 surplus
Compliance, 2024
A
Permit
14220-0015
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 3,646,506 | 6,267,829 | 2,621,323 surplus |
| 2024 | 4,483,481 | 6,267,829 | 1,784,348 surplus |
| 2023 | 3,983,499 | 6,267,829 | 2,284,330 surplus |
| 2022 | 3,992,570 | 6,268,820 | 2,276,250 surplus |
| 2021 | 4,283,764 | 5,198,353 | 914,589 surplus |
| 2020 | 3,600,915 | 5,442,880 | 1,841,965 surplus |
| 2019 | 4,207,263 | 5,557,480 | 1,350,217 surplus |
| 2018 | 4,683,105 | 5,671,684 | 988,579 surplus |
| 2017 | 4,620,499 | 5,784,481 | 1,163,982 surplus |
| 2016 | 3,911,756 | 5,896,192 | 1,984,436 surplus |
| 2015 | 4,452,128 | 6,006,712 | 1,554,584 surplus |
| 2014 | 4,223,992 | 6,116,092 | 1,892,100 surplus |
| 2013 | 3,948,261 | 6,224,201 | 2,275,940 surplus |
Verified emissions changed by -7.6% from 2013 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
Free allocation exceeded verified emissions in 2025, by 2,621,323 allowances.
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
CBAM context
This activity falls in the iron and steel sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.
| 2026 | 2027 | 2028 | 2029 | 2030 | 2031 | 2032 | 2033 | 2034 |
|---|---|---|---|---|---|---|---|---|
| 97.5% | 95% | 90% | 77.5% | 51.5% | 39% | 26.5% | 14% | 0% |
Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.
Proposed change
A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.
More on CBAM: the India CBAM Center and what CBAM is and how it works.
Nearby installations
Production of pig iron or steel installations in Germany, largest first.
- Integriertes Hüttenwerk Duisburg 6,705,307 t in 2025
- Glocke Duisburg 3,901,188 t in 2025
- Glocke Salzgitter 3,497,812 t in 2025
- Einheitliche Anlage Bremen 2,170,849 t in 2025
- Roheisen-und Stahlerzeugung 1,289,771 t in 2025
Questions about Roheisenerzeugung Dillingen
How much did Roheisenerzeugung Dillingen emit in 2025?
3,646,506 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did Roheisenerzeugung Dillingen receive?
6,267,829 in 2025.
Did Roheisenerzeugung Dillingen surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.