SCHWENK Werk Karlstadt is a production of cement clinker installation in Germany. In 2025 it reported 553,128 tonnes of verified emissions against 571,538 free allowances.

Key figures

Country

Germany

Activity

Production of cement clinker

Installation ID

DE 84

Verified emissions, 2025

553,128 tCO₂e

Free allocation, 2025

571,538 allowances

Allowance position, 2025

18,410 surplus

Compliance, 2024

A

Permit

14230-0013

Data as of

1 April 2026

Emissions and free allocation by year

Verified emissions Free allocation
Verified emissions and free allocation of SCHWENK Werk KarlstadtVerified emissions and free allocation from 2013 to 2025.0250k500k750k1M2013 verified emissions: 587,565 t2014 verified emissions: 587,064 t2015 verified emissions: 605,217 t2016 verified emissions: 581,344 t2017 verified emissions: 580,338 t2018 verified emissions: 613,356 t2019 verified emissions: 603,301 t2020 verified emissions: 581,597 t2021 verified emissions: 632,068 t2022 verified emissions: 613,261 t2023 verified emissions: 543,135 t2024 verified emissions: 480,555 t2025 verified emissions: 553,128 t2013 free allocation: 585,664 t2014 free allocation: 575,472 t2015 free allocation: 565,160 t2016 free allocation: 554,741 t2017 free allocation: 544,212 t2018 free allocation: 533,582 t2019 free allocation: 522,818 t2020 free allocation: 512,020 t2021 free allocation: 572,250 t2022 free allocation: 572,250 t2023 free allocation: 572,057 t2024 free allocation: 571,714 t2025 free allocation: 571,538 t2013201520172019202120232025
YearVerified emissions (t) Free allocationPosition
2025 553,128 571,538 18,410 surplus
2024 480,555 571,714 91,159 surplus
2023 543,135 572,057 28,922 surplus
2022 613,261 572,250 41,011 short
2021 632,068 572,250 59,818 short
2020 581,597 512,020 69,577 short
2019 603,301 522,818 80,483 short
2018 613,356 533,582 79,774 short
2017 580,338 544,212 36,126 short
2016 581,344 554,741 26,603 short
2015 605,217 565,160 40,057 short
2014 587,064 575,472 11,592 short
2013 587,565 585,664 1,901 short

Verified emissions changed by -5.9% from 2013 to 2025.

Source: European Commission, Union Registry · Data as of 1 April 2026

Allowance position

Free allocation exceeded verified emissions in 2025, by 18,410 allowances.

Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.

CBAM context

This activity falls in the cement sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.

Free allocation remaining for CBAM-covered products, by year
202620272028202920302031203220332034
97.5%95%90%77.5%51.5%39%26.5%14%0%

Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.

Proposed change

A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.

More on CBAM: the India CBAM Center and what CBAM is and how it works.

Nearby installations

Production of cement clinker installations in Germany, largest first.

Questions about SCHWENK Werk Karlstadt

How much did SCHWENK Werk Karlstadt emit in 2025?

553,128 tonnes of verified emissions, per EU Union Registry compliance data.

How many free allowances did SCHWENK Werk Karlstadt receive?

571,538 in 2025.

Did SCHWENK Werk Karlstadt surrender enough allowances?

Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.