Wärmöfen Warmbreitbandwalzwerk

Wärmöfen Warmbreitbandwalzwerk is a production or processing of ferrous metals installation in Germany. In 2025 it reported 285,316 tonnes of verified emissions against 260,105 free allowances.

Key figures

Country

Germany

Activity

Production or processing of ferrous metals

Installation ID

DE 2495

Verified emissions, 2025

285,316 tCO₂e

Free allocation, 2025

260,105 allowances

Allowance position, 2025

25,211 short

Compliance, 2024

A

Permit

14225-0002

Data as of

1 April 2026

Emissions and free allocation by year

Verified emissions Free allocation
Verified emissions and free allocation of Wärmöfen WarmbreitbandwalzwerkVerified emissions and free allocation from 2013 to 2025.0125k250k375k500k2013 verified emissions: 251,875 t2014 verified emissions: 249,717 t2015 verified emissions: 260,822 t2016 verified emissions: 288,183 t2017 verified emissions: 291,814 t2018 verified emissions: 313,238 t2019 verified emissions: 309,126 t2020 verified emissions: 265,535 t2021 verified emissions: 301,634 t2022 verified emissions: 272,229 t2023 verified emissions: 264,953 t2024 verified emissions: 274,514 t2025 verified emissions: 285,316 t2013 free allocation: 303,610 t2014 free allocation: 298,336 t2015 free allocation: 293,001 t2016 free allocation: 287,610 t2017 free allocation: 282,161 t2018 free allocation: 276,659 t2019 free allocation: 271,089 t2020 free allocation: 265,498 t2021 free allocation: 251,424 t2022 free allocation: 245,455 t2023 free allocation: 251,739 t2024 free allocation: 260,105 t2025 free allocation: 260,105 t2013201520172019202120232025
YearVerified emissions (t) Free allocationPosition
2025 285,316 260,105 25,211 short
2024 274,514 260,105 14,409 short
2023 264,953 251,739 13,214 short
2022 272,229 245,455 26,774 short
2021 301,634 251,424 50,210 short
2020 265,535 265,498 37 short
2019 309,126 271,089 38,037 short
2018 313,238 276,659 36,579 short
2017 291,814 282,161 9,653 short
2016 288,183 287,610 573 short
2015 260,822 293,001 32,179 surplus
2014 249,717 298,336 48,619 surplus
2013 251,875 303,610 51,735 surplus

Verified emissions changed by +13.3% from 2013 to 2025.

Source: European Commission, Union Registry · Data as of 1 April 2026

Allowance position

In 2025, verified emissions exceeded free allocation by 25,211 allowances, which the operator had to obtain.

Illustrative value at the latest reference price of €84.87 (29 September 2026): €2,139,658. Not the installation's actual cost, which depends on when and how it acquired allowances.

Price source: EU ETS primary auctions · latest price

Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.

CBAM context

This activity falls in the iron and steel sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.

Free allocation remaining for CBAM-covered products, by year
202620272028202920302031203220332034
97.5%95%90%77.5%51.5%39%26.5%14%0%

Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.

Proposed change

A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.

More on CBAM: the India CBAM Center and what CBAM is and how it works.

Nearby installations

Production or processing of ferrous metals installations in Germany, largest first.

Questions about Wärmöfen Warmbreitbandwalzwerk

How much did Wärmöfen Warmbreitbandwalzwerk emit in 2025?

285,316 tonnes of verified emissions, per EU Union Registry compliance data.

How many free allowances did Wärmöfen Warmbreitbandwalzwerk receive?

260,105 in 2025.

Did Wärmöfen Warmbreitbandwalzwerk surrender enough allowances?

Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.