Duna-Dráva Cement Kft. Beremendi Cementgyár
Duna-Dráva Cement Kft. Beremendi Cementgyár is a production of cement clinker installation in Hungary. In 2025 it reported 175,353 tonnes of verified emissions against 184,699 free allowances.
Key figures
Country
Activity
Installation ID
HU 48
Verified emissions, 2025
175,353 tCO₂e
Free allocation, 2025
184,699 allowances
Allowance position, 2025
9,346 surplus
Compliance, 2024
A
Permit
HU-UHG5381-6A-04
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 175,353 | 184,699 | 9,346 surplus |
| 2024 | 162,962 | 311,108 | 148,146 surplus |
| 2023 | 222,670 | 400,310 | 177,640 surplus |
| 2022 | 378,394 | 400,310 | 21,916 surplus |
| 2021 | 458,744 | 386,304 | 72,440 short |
| 2020 | 391,234 | 483,448 | 92,214 surplus |
| 2019 | 427,729 | 493,627 | 65,898 surplus |
| 2018 | 464,036 | 503,771 | 39,735 surplus |
| 2017 | 363,206 | 513,790 | 150,584 surplus |
| 2016 | 288,356 | 523,712 | 235,356 surplus |
| 2015 | 292,870 | 533,529 | 240,659 surplus |
| 2014 | 286,584 | 543,244 | 256,660 surplus |
| 2013 | 286,581 | 552,847 | 266,266 surplus |
Verified emissions changed by -38.8% from 2013 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
Free allocation exceeded verified emissions in 2025, by 9,346 allowances.
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
CBAM context
This activity falls in the cement sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.
| 2026 | 2027 | 2028 | 2029 | 2030 | 2031 | 2032 | 2033 | 2034 |
|---|---|---|---|---|---|---|---|---|
| 97.5% | 95% | 90% | 77.5% | 51.5% | 39% | 26.5% | 14% | 0% |
Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.
Proposed change
A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.
More on CBAM: the India CBAM Center and what CBAM is and how it works.
Nearby installations
Production of cement clinker installations in Hungary, largest first.
- Duna-Dráva Cement Korlátolt Felelősségű Társaság 375,113 t in 2025
- Királyegyházi Cementgyár 80,368 t in 2025
Questions about Duna-Dráva Cement Kft. Beremendi Cementgyár
How much did Duna-Dráva Cement Kft. Beremendi Cementgyár emit in 2025?
175,353 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did Duna-Dráva Cement Kft. Beremendi Cementgyár receive?
184,699 in 2025.
Did Duna-Dráva Cement Kft. Beremendi Cementgyár surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.