Duna-Dráva Cement Korlátolt Felelősségű Társaság
Duna-Dráva Cement Korlátolt Felelősségű Társaság is a production of cement clinker installation in Hungary. In 2025 it reported 375,113 tonnes of verified emissions against 379,480 free allowances.
Key figures
Country
Activity
Installation ID
HU 47
Verified emissions, 2025
375,113 tCO₂e
Free allocation, 2025
379,480 allowances
Allowance position, 2025
4,367 surplus
Compliance, 2024
A
Permit
HU-UHG5260-6A-04
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 375,113 | 379,480 | 4,367 surplus |
| 2024 | 357,859 | 379,833 | 21,974 surplus |
| 2023 | 341,718 | 380,419 | 38,701 surplus |
| 2022 | 396,703 | 446,052 | 49,349 surplus |
| 2021 | 514,411 | 446,052 | 68,359 short |
| 2020 | 467,892 | 508,030 | 40,138 surplus |
| 2019 | 525,616 | 518,727 | 6,889 short |
| 2018 | 437,518 | 529,387 | 91,869 surplus |
| 2017 | 460,229 | 539,915 | 79,686 surplus |
| 2016 | 487,754 | 550,342 | 62,588 surplus |
| 2015 | 454,134 | 560,658 | 106,524 surplus |
| 2014 | 374,262 | 570,867 | 196,605 surplus |
| 2013 | 323,360 | 580,958 | 257,598 surplus |
Verified emissions changed by +16% from 2013 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
Free allocation exceeded verified emissions in 2025, by 4,367 allowances.
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
CBAM context
This activity falls in the cement sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.
| 2026 | 2027 | 2028 | 2029 | 2030 | 2031 | 2032 | 2033 | 2034 |
|---|---|---|---|---|---|---|---|---|
| 97.5% | 95% | 90% | 77.5% | 51.5% | 39% | 26.5% | 14% | 0% |
Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.
Proposed change
A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.
More on CBAM: the India CBAM Center and what CBAM is and how it works.
Nearby installations
Production of cement clinker installations in Hungary, largest first.
- Duna-Dráva Cement Kft. Beremendi Cementgyár 175,353 t in 2025
- Királyegyházi Cementgyár 80,368 t in 2025
Questions about Duna-Dráva Cement Korlátolt Felelősségű Társaság
How much did Duna-Dráva Cement Korlátolt Felelősségű Társaság emit in 2025?
375,113 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did Duna-Dráva Cement Korlátolt Felelősségű Társaság receive?
379,480 in 2025.
Did Duna-Dráva Cement Korlátolt Felelősségű Társaság surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.