Dublin Bay Power Plant

Dublin Bay Power Plant is a combustion of fuels installation in Ireland. In 2025 it reported 886,437 tonnes of verified emissions against 0 free allowances.

Key figures

Country

Ireland

Activity

Combustion of fuels

Installation ID

IE 14

Verified emissions, 2025

886,437 tCO₂e

Free allocation, 2025

None

Allowance position, 2025

886,437 short

Compliance, 2024

A

Permit

IE-GHG016

Data as of

1 April 2026

Emissions and free allocation by year

Verified emissions Free allocation
Verified emissions and free allocation of Dublin Bay Power PlantVerified emissions and free allocation from 2013 to 2025.0500k1M1.5M2M2013 verified emissions: 1,088,618 t2014 verified emissions: 1,094,267 t2015 verified emissions: 1,137,015 t2016 verified emissions: 995,019 t2017 verified emissions: 1,042,972 t2018 verified emissions: 1,111,570 t2019 verified emissions: 848,621 t2020 verified emissions: 742,726 t2021 verified emissions: 679,932 t2022 verified emissions: 683,415 t2023 verified emissions: 751,883 t2024 verified emissions: 879,184 t2025 verified emissions: 886,437 t2013201520172019202120232025
YearVerified emissions (t) Free allocationPosition
2025 886,437 none 886,437 short
2024 879,184 none 879,184 short
2023 751,883 none 751,883 short
2022 683,415 none 683,415 short
2021 679,932 none 679,932 short
2020 742,726 none 742,726 short
2019 848,621 none 848,621 short
2018 1,111,570 none 1,111,570 short
2017 1,042,972 none 1,042,972 short
2016 995,019 none 995,019 short
2015 1,137,015 none 1,137,015 short
2014 1,094,267 none 1,094,267 short
2013 1,088,618 none 1,088,618 short

Verified emissions changed by -18.6% from 2013 to 2025.

Source: European Commission, Union Registry · Data as of 1 April 2026

Allowance position

In 2025, verified emissions exceeded free allocation by 886,437 allowances, which the operator had to obtain.

Illustrative value at the latest reference price of €85.90 (28 September 2026): €76,144,938. Not the installation's actual cost, which depends on when and how it acquired allowances.

Price source: EU ETS primary auctions · latest price

Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.

Nearby installations

Combustion of fuels installations in Ireland, largest first.

Questions about Dublin Bay Power Plant

How much did Dublin Bay Power Plant emit in 2025?

886,437 tonnes of verified emissions, per EU Union Registry compliance data.

Did Dublin Bay Power Plant surrender enough allowances?

Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.