Cargill Bergen op Zoom BKG 1 is a combustion of fuels installation in Netherlands. In 2025 it reported 28,236 tonnes of verified emissions against 38,422 free allowances.
Key figures
Country
Activity
Installation ID
NL 53
Verified emissions, 2025
28,236 tCO₂e
Free allocation, 2025
38,422 allowances
Allowance position, 2025
10,186 surplus
Compliance, 2024
A
Permit
NL-200400215
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 28,236 | 38,422 | 10,186 surplus |
| 2024 | 24,604 | 44,066 | 19,462 surplus |
| 2023 | 25,429 | 54,855 | 29,426 surplus |
| 2022 | 41,443 | 54,716 | 13,273 surplus |
| 2021 | 51,161 | 54,716 | 3,555 surplus |
| 2020 | 30,012 | 52,156 | 22,144 surplus |
| 2019 | 35,292 | 53,254 | 17,962 surplus |
| 2018 | 34,405 | 54,349 | 19,944 surplus |
| 2017 | 39,606 | 55,430 | 15,824 surplus |
| 2016 | 42,410 | 56,500 | 14,090 surplus |
| 2015 | 11,519 | 57,559 | 46,040 surplus |
| 2014 | 9,348 | 58,607 | 49,259 surplus |
| 2013 | 5,707 | 59,643 | 53,936 surplus |
Verified emissions changed by +394.8% from 2013 to 2025.
Source: European Commission, Union Registry ยท Data as of 1 April 2026
Allowance position
Free allocation exceeded verified emissions in 2025, by 10,186 allowances.
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
Nearby installations
Combustion of fuels installations in Netherlands, largest first.
- Vattenfall Power Velsen 3,745,786 t in 2025
- RWE Eemshaven Centrale 3,596,911 t in 2025
- Chemelot BKG 01 2,820,546 t in 2025
- Power Plant Rotterdam B.V. 2,223,444 t in 2025
- Uniper Centrale Maasvlakte 2,001,910 t in 2025
Questions about Cargill Bergen op Zoom BKG 1
How much did Cargill Bergen op Zoom BKG 1 emit in 2025?
28,236 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did Cargill Bergen op Zoom BKG 1 receive?
38,422 in 2025.
Did Cargill Bergen op Zoom BKG 1 surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.