LISAHALLY POWER STATION
LISAHALLY POWER STATION is a combustion of fuels installation in Northern Ireland. It last reported verified emissions for 2024: 9,106 tonnes.
Key figures
Country
Activity
Installation ID
XI 207642
Verified emissions, 2024
9,106 tCO₂e
Free allocation, 2024
None
Allowance position, 2024
Not available
Compliance, 2024
A
Permit
UK-N-IN-13269
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2024 | 9,106 | none | 9,106 short |
| 2023 | 9,144 | none | 9,144 short |
| 2022 | 9,191 | none | 9,191 short |
| 2021 | 9,623 | none | 9,623 short |
| 2020 | 8,436 | none | 8,436 short |
| 2019 | 9,103 | none | 9,103 short |
| 2018 | 9,832 | none | 9,832 short |
| 2017 | 6,092 | none | 6,092 short |
| 2016 | 8,001 | none | 8,001 short |
| 2015 | 2,208 | none | 2,208 short |
Verified emissions changed by +312.4% from 2015 to 2024.
Source: European Commission, Union Registry ยท Data as of 1 April 2026
Allowance position
No verified emissions were reported for 2025, so there is no position for the latest year.
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
Nearby installations
Combustion of fuels installations in Northern Ireland, largest first.
- Ballylumford Power Station 748,697 t in 2025
- Coolkeeragh ESB Ltd 524,083 t in 2025
- Knockmore Hill CHP Plant 3,720 t in 2025
Questions about LISAHALLY POWER STATION
How much did LISAHALLY POWER STATION emit in 2024?
9,106 tonnes of verified emissions, per EU Union Registry compliance data.
Did LISAHALLY POWER STATION surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.