Energa ELEKTROWNIE OSTROŁĘKA SA

Energa ELEKTROWNIE OSTROŁĘKA SA is a combustion of fuels installation in Poland. In 2025 it reported 1,550,795 tonnes of verified emissions against 13,114 free allowances.

Key figures

Country

Poland

Activity

Combustion of fuels

Installation ID

PL 20

Verified emissions, 2025

1,550,795 tCO₂e

Free allocation, 2025

13,114 allowances

Allowance position, 2025

1,537,681 short

Compliance, 2024

A

Permit

PL-0020-05

Data as of

1 April 2026

Emissions and free allocation by year

Verified emissions Free allocation
Verified emissions and free allocation of Energa ELEKTROWNIE OSTROŁĘKA SAVerified emissions and free allocation from 2013 to 2025.01.3M2.5M3.8M5M2013 verified emissions: 2,590,758 t2014 verified emissions: 2,822,961 t2015 verified emissions: 2,016,088 t2016 verified emissions: 2,300,685 t2017 verified emissions: 2,320,639 t2018 verified emissions: 2,271,776 t2019 verified emissions: 1,849,931 t2020 verified emissions: 1,476,893 t2021 verified emissions: 2,329,460 t2022 verified emissions: 2,739,890 t2023 verified emissions: 1,602,165 t2024 verified emissions: 1,050,662 t2025 verified emissions: 1,550,795 t2013 free allocation: 1,349,730 t2014 free allocation: 1,247,687 t2015 free allocation: 1,084,471 t2016 free allocation: 878,346 t2017 free allocation: 702,816 t2018 free allocation: 562,222 t2019 free allocation: 421,122 t2020 free allocation: 25,240 t2021 free allocation: 14,852 t2022 free allocation: 14,470 t2023 free allocation: 14,191 t2024 free allocation: 13,489 t2025 free allocation: 13,114 t2013201520172019202120232025
YearVerified emissions (t) Free allocationPosition
2025 1,550,795 13,114 1,537,681 short
2024 1,050,662 13,489 1,037,173 short
2023 1,602,165 14,191 1,587,974 short
2022 2,739,890 14,470 2,725,420 short
2021 2,329,460 14,852 2,314,608 short
2020 1,476,893 25,240 1,451,653 short
2019 1,849,931 421,122 1,428,809 short
2018 2,271,776 562,222 1,709,554 short
2017 2,320,639 702,816 1,617,823 short
2016 2,300,685 878,346 1,422,339 short
2015 2,016,088 1,084,471 931,617 short
2014 2,822,961 1,247,687 1,575,274 short
2013 2,590,758 1,349,730 1,241,028 short

Verified emissions changed by -40.1% from 2013 to 2025.

Source: European Commission, Union Registry · Data as of 1 April 2026

Allowance position

In 2025, verified emissions exceeded free allocation by 1,537,681 allowances, which the operator had to obtain.

Illustrative value at the latest reference price of €85.90 (28 September 2026): €132,086,798. Not the installation's actual cost, which depends on when and how it acquired allowances.

Price source: EU ETS primary auctions · latest price

Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.

Nearby installations

Combustion of fuels installations in Poland, largest first.

Questions about Energa ELEKTROWNIE OSTROŁĘKA SA

How much did Energa ELEKTROWNIE OSTROŁĘKA SA emit in 2025?

1,550,795 tonnes of verified emissions, per EU Union Registry compliance data.

How many free allowances did Energa ELEKTROWNIE OSTROŁĘKA SA receive?

13,114 in 2025.

Did Energa ELEKTROWNIE OSTROŁĘKA SA surrender enough allowances?

Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.