WALCOWNIE

WALCOWNIE is a production or processing of ferrous metals installation in Poland. In 2025 it reported 28,190 tonnes of verified emissions against 19,218 free allowances.

Key figures

Country

Poland

Activity

Production or processing of ferrous metals

Installation ID

PL 895

Verified emissions, 2025

28,190 tCO₂e

Free allocation, 2025

19,218 allowances

Allowance position, 2025

8,972 short

Compliance, 2024

A

Permit

PL-0916-08

Data as of

1 April 2026

Emissions and free allocation by year

Verified emissions Free allocation
Verified emissions and free allocation of WALCOWNIEVerified emissions and free allocation from 2013 to 2025.012.5k25k37.5k50k2013 verified emissions: 28,700 t2014 verified emissions: 31,862 t2015 verified emissions: 34,906 t2016 verified emissions: 34,988 t2017 verified emissions: 34,474 t2018 verified emissions: 33,271 t2019 verified emissions: 33,850 t2020 verified emissions: 28,984 t2021 verified emissions: 31,548 t2022 verified emissions: 28,294 t2023 verified emissions: 23,269 t2024 verified emissions: 26,329 t2025 verified emissions: 28,190 t2013 free allocation: 41,914 t2014 free allocation: 41,187 t2015 free allocation: 40,450 t2016 free allocation: 39,705 t2017 free allocation: 38,953 t2018 free allocation: 38,194 t2019 free allocation: 37,425 t2020 free allocation: 36,653 t2021 free allocation: 25,967 t2022 free allocation: 25,967 t2023 free allocation: 25,967 t2024 free allocation: 19,978 t2025 free allocation: 19,218 t2013201520172019202120232025
YearVerified emissions (t) Free allocationPosition
2025 28,190 19,218 8,972 short
2024 26,329 19,978 6,351 short
2023 23,269 25,967 2,698 surplus
2022 28,294 25,967 2,327 short
2021 31,548 25,967 5,581 short
2020 28,984 36,653 7,669 surplus
2019 33,850 37,425 3,575 surplus
2018 33,271 38,194 4,923 surplus
2017 34,474 38,953 4,479 surplus
2016 34,988 39,705 4,717 surplus
2015 34,906 40,450 5,544 surplus
2014 31,862 41,187 9,325 surplus
2013 28,700 41,914 13,214 surplus

Verified emissions changed by -1.8% from 2013 to 2025.

Source: European Commission, Union Registry · Data as of 1 April 2026

Allowance position

In 2025, verified emissions exceeded free allocation by 8,972 allowances, which the operator had to obtain.

Illustrative value at the latest reference price of €84.87 (29 September 2026): €761,454. Not the installation's actual cost, which depends on when and how it acquired allowances.

Price source: EU ETS primary auctions · latest price

Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.

CBAM context

This activity falls in the iron and steel sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.

Free allocation remaining for CBAM-covered products, by year
202620272028202920302031203220332034
97.5%95%90%77.5%51.5%39%26.5%14%0%

Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.

Proposed change

A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.

More on CBAM: the India CBAM Center and what CBAM is and how it works.

Nearby installations

Production or processing of ferrous metals installations in Poland, largest first.

Questions about WALCOWNIE

How much did WALCOWNIE emit in 2025?

28,190 tonnes of verified emissions, per EU Union Registry compliance data.

How many free allowances did WALCOWNIE receive?

19,218 in 2025.

Did WALCOWNIE surrender enough allowances?

Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.