WALCOWNIE ARCELORMITTAL KRAKÓW

WALCOWNIE ARCELORMITTAL KRAKÓW is a production or processing of ferrous metals installation in Poland. In 2025 it reported 188,433 tonnes of verified emissions against 147,776 free allowances.

Key figures

Country

Poland

Activity

Production or processing of ferrous metals

Installation ID

PL 898

Verified emissions, 2025

188,433 tCO₂e

Free allocation, 2025

147,776 allowances

Allowance position, 2025

40,657 short

Compliance, 2024

A

Permit

PL-0919-08

Data as of

1 April 2026

Emissions and free allocation by year

Verified emissions Free allocation
Verified emissions and free allocation of WALCOWNIE ARCELORMITTAL KRAKÓWVerified emissions and free allocation from 2013 to 2025.0125k250k375k500k2013 verified emissions: 177,689 t2014 verified emissions: 186,933 t2015 verified emissions: 195,135 t2016 verified emissions: 224,432 t2017 verified emissions: 244,769 t2018 verified emissions: 259,109 t2019 verified emissions: 218,447 t2020 verified emissions: 181,286 t2021 verified emissions: 199,502 t2022 verified emissions: 159,692 t2023 verified emissions: 163,295 t2024 verified emissions: 189,618 t2025 verified emissions: 188,433 t2013 free allocation: 288,631 t2014 free allocation: 283,618 t2015 free allocation: 278,546 t2016 free allocation: 273,421 t2017 free allocation: 268,240 t2018 free allocation: 263,009 t2019 free allocation: 257,714 t2020 free allocation: 252,400 t2021 free allocation: 199,217 t2022 free allocation: 199,217 t2023 free allocation: 171,478 t2024 free allocation: 150,604 t2025 free allocation: 147,776 t2013201520172019202120232025
YearVerified emissions (t) Free allocationPosition
2025 188,433 147,776 40,657 short
2024 189,618 150,604 39,014 short
2023 163,295 171,478 8,183 surplus
2022 159,692 199,217 39,525 surplus
2021 199,502 199,217 285 short
2020 181,286 252,400 71,114 surplus
2019 218,447 257,714 39,267 surplus
2018 259,109 263,009 3,900 surplus
2017 244,769 268,240 23,471 surplus
2016 224,432 273,421 48,989 surplus
2015 195,135 278,546 83,411 surplus
2014 186,933 283,618 96,685 surplus
2013 177,689 288,631 110,942 surplus

Verified emissions changed by +6% from 2013 to 2025.

Source: European Commission, Union Registry · Data as of 1 April 2026

Allowance position

In 2025, verified emissions exceeded free allocation by 40,657 allowances, which the operator had to obtain.

Illustrative value at the latest reference price of €84.87 (29 September 2026): €3,450,560. Not the installation's actual cost, which depends on when and how it acquired allowances.

Price source: EU ETS primary auctions · latest price

Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.

CBAM context

This activity falls in the iron and steel sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.

Free allocation remaining for CBAM-covered products, by year
202620272028202920302031203220332034
97.5%95%90%77.5%51.5%39%26.5%14%0%

Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.

Proposed change

A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.

More on CBAM: the India CBAM Center and what CBAM is and how it works.

Nearby installations

Production or processing of ferrous metals installations in Poland, largest first.

Questions about WALCOWNIE ARCELORMITTAL KRAKÓW

How much did WALCOWNIE ARCELORMITTAL KRAKÓW emit in 2025?

188,433 tonnes of verified emissions, per EU Union Registry compliance data.

How many free allowances did WALCOWNIE ARCELORMITTAL KRAKÓW receive?

147,776 in 2025.

Did WALCOWNIE ARCELORMITTAL KRAKÓW surrender enough allowances?

Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.