S.N.G.N. Romgaz S.A. - SPEE Iernut - CTE Iernut
S.N.G.N. Romgaz S.A. - SPEE Iernut - CTE Iernut is a combustion of fuels installation in Romania. In 2025 it reported 428,029 tonnes of verified emissions against 0 free allowances.
Key figures
Country
Activity
Installation ID
RO 108
Verified emissions, 2025
428,029 tCO₂e
Free allocation, 2025
None
Allowance position, 2025
428,029 short
Compliance, 2024
A
Permit
58
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 428,029 | none | 428,029 short |
| 2024 | 500,230 | none | 500,230 short |
| 2023 | 543,772 | none | 543,772 short |
| 2022 | 640,740 | none | 640,740 short |
| 2021 | 378,841 | none | 378,841 short |
| 2020 | 531,072 | none | 531,072 short |
| 2019 | 333,688 | 137,441 | 196,247 short |
| 2018 | 646,851 | 274,882 | 371,969 short |
| 2017 | 1,024,682 | 412,322 | 612,360 short |
| 2016 | 895,835 | 549,763 | 346,072 short |
| 2015 | 984,053 | 687,204 | 296,849 short |
| 2014 | 828,793 | 824,645 | 4,148 short |
| 2013 | 507,620 | 962,085 | 454,465 surplus |
Verified emissions changed by -15.7% from 2013 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
In 2025, verified emissions exceeded free allocation by 428,029 allowances, which the operator had to obtain.
Illustrative value at the latest reference price of €84.87 (29 September 2026): €36,326,821. Not the installation's actual cost, which depends on when and how it acquired allowances.
Price source: EU ETS primary auctions · latest price
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
Nearby installations
Combustion of fuels installations in Romania, largest first.
- SC C.E. OLTENIA SA - SUC. ELECTROCENTRALE ROVINARI 2,574,658 t in 2025
- S Complexul Energetic Oltenia SA-SE Turceni 1,839,494 t in 2025
- Centrala de Cogenerare cu Ciclu Combinat- Brazi 1,713,237 t in 2025
- PETROBRAZI 1,008,318 t in 2025
- SOCIETATEA ELECTROCENTRALE CRAIOVA SA 904,913 t in 2025
Questions about S.N.G.N. Romgaz S.A. - SPEE Iernut - CTE Iernut
How much did S.N.G.N. Romgaz S.A. - SPEE Iernut - CTE Iernut emit in 2025?
428,029 tonnes of verified emissions, per EU Union Registry compliance data.
Did S.N.G.N. Romgaz S.A. - SPEE Iernut - CTE Iernut surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.