Centro de Datos MAD01
Centro de Datos MAD01 is a combustion of fuels installation in Spain. In 2025 it reported 331 tonnes of verified emissions against 0 free allowances.
Key figures
Country
Activity
Installation ID
ES 218820
Verified emissions, 2025
331 tCO₂e
Free allocation, 2025
None
Allowance position, 2025
331 short
Compliance, 2024
A
Permit
ES15281C21-244614
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 331 | none | 331 short |
| 2024 | 292 | none | 292 short |
| 2023 | 178 | none | 178 short |
| 2022 | 131 | none | 131 short |
Verified emissions changed by +152.7% from 2022 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
In 2025, verified emissions exceeded free allocation by 331 allowances, which the operator had to obtain.
Illustrative value at the latest reference price of €85.90 (28 September 2026): €28,433. Not the installation's actual cost, which depends on when and how it acquired allowances.
Price source: EU ETS primary auctions · latest price
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
Nearby installations
Combustion of fuels installations in Spain, largest first.
- Aboño Generaciones Eléctricas, S.L.U. 2,642,623 t in 2025
- Unión Eléctr. de Canarias Generación-CT Granadilla 1,989,419 t in 2025
- Unión Eléct.Canarias Generac.-CT Barranco Tirajana 1,660,505 t in 2025
- CCC - Cartagena 1,133,989 t in 2025
- CCC. - Sagunto 1,085,196 t in 2025
Questions about Centro de Datos MAD01
How much did Centro de Datos MAD01 emit in 2025?
331 tonnes of verified emissions, per EU Union Registry compliance data.
Did Centro de Datos MAD01 surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.