Bundled Wind Power Project by Woodside Fashions Limited & Group (EKIESL-CDM.June-16-01)
Registry
Gold Standard
Project ID
GLD5256
Country
Category
Renewable Energy
Methodology
Status
Not stated
Credits Issued
60,866 tCO₂e
Credits Retired
56,776 tCO₂e
Data as of
1 June 2026
Credit Passport
How to read itIssuance and retirement by vintage
| Vintage | Issued (tCO₂e) | Retired (tCO₂e) |
|---|---|---|
| 2022 | 10,532 | 6,851 |
| 2021 | 10,200 | 9,996 |
| 2020 | 23,001 | 23,001 |
| 2019 | 12,539 | 12,334 |
| 2018 | 4,594 | 4,594 |
Source: Registry records · Data as of 1 June 2026
Credit Passport in detail
ICVCM quality status
Methodology assessed by ICVCM and not approved.
- Programme: Gold Standard, CCP-eligible since April 2024.
- AMS-I.D. - Grid connected renewable electricity generation - 1.0-18.0: does not meet the Core Carbon Principles
The CCP label is applied to credits by the registry, issuance by issuance. An approved methodology means credits from this project can be eligible; it does not mean every credit carries the label.
Source: ICVCM assessment decisions · Decisions read 19 September 2026
CORSIA screen
A screen against published ICAO criteria, not an eligibility determination.
First phase, 2024 to 2026
- ProgrammePassesGold Standard is approved by ICAO for 2024 to 2026.
- DatesCannot be confirmed from available dataCredits issued for vintages 2021 to 2022. The start of the first crediting period is recorded by Gold Standard as 31 January 2018, but whether that is the first period is not in registry data.
- Host country authorisationCannot be confirmed from available dataAuthorisation is granted per activity. This screen cannot confirm whether this project holds a Letter of Authorization.
Second phase, 2027 to 2029
- ProgrammePassesGold Standard is approved by ICAO for 2027 to 2029.
- DatesCannot be confirmed from available dataCredits issued for vintages 2021 to 2022. The start of the first crediting period is recorded by Gold Standard as 31 January 2018, but whether that is the first period is not in registry data.
Programme-specific exclusions were not assessed. Host country context is under Article 6 below.
Source: ICAO eligibility decisions and registry records · Criteria verified 25 September 2026
India and Article 6
- Bilateral agreements
- 2
- Authority for the Paris Agreement Crediting Mechanism
- Appointed
- Participation requirements for the Mechanism
- Published
- Cooperative approaches
- 0
- Article 6.2 activities
- 0
- Crediting Mechanism activities approved by the host
- 0
- Crediting Mechanism activities registered
- 0
This is country-level context. It does not show whether this project is authorised.
Source: UN Article 6 tracking · Data as of 4 September 2026
Recorded buyers
No organisation named as beneficiary in registry records.
Retired credits from this project? See what a company can still say about them under the EU green claims rules.
Source: Registry records · Data as of 1 June 2026
Declared SDG contributions
Goals the project declared to its registry. CRBN.credit does not measure these outcomes.
Source: Gold Standard registry · Data as of 17 September 2026
Gold Standard's current record
Gold Standard registry · as of 28 October 2026
Status
Gold Standard Certified Project
Project type
Wind
Scale
Small scale
Structure
Standalone project
Developer
EKI Energy Services Limited
Crediting period
31 Jan 2018 to 30 Jan 2023
Expected per year
16,920 tCO₂e, as estimated at registration
Bundled Wind Power Project by Woodside Fashions Limited & Group (EKIESL-CDM.June-16-01) is registered with Gold Standard under the ams-i-d protocol, located in India. As of 1 June 2026, registry records show 60,866 tonnes issued and 56,776 tonnes retired. This reflects registry-reported figures, not an independent quality assessment.
Related
Similar projects
- Electricity generation from mustard crop residues: Tonk India 514,017 t issued
- Wind Power Project at Anthiyur, Tamil Nadu 508,222 t issued
- Bundled Solar VCS Project by EKIESL (EKIESL- VCS.Oct 2016-01) 417,404 t issued
- 15 MW Grid Connected Renewable Energy Wind Turbine in Karnataka 277,134 t issued
- Biomass based power project of VPL 270,973 t issued
Same methodology and country, largest issuance first.
Questions about this project
How many credits has Bundled Wind Power Project by Woodside Fashions Limited & Group (EKIESL-CDM.June-16-01) issued?
60,866 tonnes of credits have been issued and 56,776 retired, according to registry records as of 1 June 2026.
What is the ICVCM status of this project's methodology?
Methodology assessed by ICVCM and not approved. The CCP label is applied to credits by the registry, issuance by issuance.
Registry data as of June 1, 2026