Erzurum Aziziye Solar Power Plant

Registry Record

Registry

Gold Standard

Project ID

GLD7493

Country

Türkiye

Category

Renewable Energy

Methodology

ams-i-d

Status

Not stated

Credits Issued

78,017 tCO₂e

Credits Retired

20,651 tCO₂e

Data as of

1 June 2026

Issuance and retirement by vintage

Issued Retired
Issuance and retirement by vintageVintages 2019 to 2025: 78,017 tonnes issued and 20,651 retired.05k10k15k20k2019 issued: 12,704 tonnes2019 retired: 12,704 tonnes20192020 issued: 12,733 tonnes2020 retired: 7,686 tonnes20202021 issued: 13,062 tonnes2021 retired: 261 tonnes20212022 issued: 12,626 tonnes20222023 issued: 11,756 tonnes20232024 issued: 11,169 tonnes20242025 issued: 3,967 tonnes2025
VintageIssued (tCO₂e)Retired (tCO₂e)
20253,967none
202411,169none
202311,756none
202212,626none
202113,062261
202012,7337,686
201912,70412,704

Source: Registry records · Data as of 1 June 2026

Credit Passport in detail

ICVCM quality status

Methodology assessed by ICVCM and not approved.

  • Programme: Gold Standard, CCP-eligible since April 2024.
  • AMS-I.D. - Grid connected renewable electricity generation - 1.0-18.0: does not meet the Core Carbon Principles

The CCP label is applied to credits by the registry, issuance by issuance. An approved methodology means credits from this project can be eligible; it does not mean every credit carries the label.

Source: ICVCM assessment decisions · Decisions read 19 September 2026

What this layer checks

CORSIA screen

A screen against published ICAO criteria, not an eligibility determination.

First phase, 2024 to 2026

  • ProgrammePassesGold Standard is approved by ICAO for 2024 to 2026.
  • DatesCannot be confirmed from available dataCredits issued for vintages 2021 to 2025. The start of the first crediting period is recorded by Gold Standard as 4 January 2019, but whether that is the first period is not in registry data.
  • Host country authorisationCannot be confirmed from available dataAuthorisation is granted per activity. This screen cannot confirm whether this project holds a Letter of Authorization.

Second phase, 2027 to 2029

  • ProgrammePassesGold Standard is approved by ICAO for 2027 to 2029.
  • DatesCannot be confirmed from available dataCredits issued for vintages 2021 to 2025. The start of the first crediting period is recorded by Gold Standard as 4 January 2019, but whether that is the first period is not in registry data.

Programme-specific exclusions were not assessed. Host country context is under Article 6 below.

Source: ICAO eligibility decisions and registry records · Criteria verified 25 September 2026

What this layer checks

Türkiye and Article 6

Bilateral agreements
0
Authority for the Paris Agreement Crediting Mechanism
Appointed
Participation requirements for the Mechanism
Not published
Cooperative approaches
0
Article 6.2 activities
0
Crediting Mechanism activities approved by the host
0
Crediting Mechanism activities registered
0

This is country-level context. It does not show whether this project is authorised.

Source: UN Article 6 tracking · Data as of 4 September 2026

What this layer checks

Recorded buyers

No organisation named as beneficiary in registry records.

Retired credits from this project? See what a company can still say about them under the EU green claims rules.

Source: Registry records · Data as of 1 June 2026

What this layer checks

Declared SDG contributions

Goals the project declared to its registry. CRBN.credit does not measure these outcomes.

Goal 7: Affordable and Clean EnergyGoal 8: Decent Work and Economic GrowthGoal 13: Climate Action

Source: Gold Standard registry · Data as of 17 September 2026

What this layer checks

Gold Standard's current record

Gold Standard registry · as of 28 October 2026

Status

Gold Standard Certified Project

Project type

Solar Thermal - Electricity

Scale

Small scale

Structure

Standalone project

Developer

Galata Wind Enerji A.S.

Crediting period

4 Jan 2019 to 3 Jan 2029

Expected per year

14,067 tCO₂e, as estimated at registration

Erzurum Aziziye Solar Power Plant is registered with Gold Standard under the ams-i-d protocol, located in Türkiye. As of 1 June 2026, registry records show 78,017 tonnes issued and 20,651 tonnes retired. This reflects registry-reported figures, not an independent quality assessment.

Related

Similar projects

Same methodology and country, largest issuance first.

Questions about this project

How many credits has Erzurum Aziziye Solar Power Plant issued?

78,017 tonnes of credits have been issued and 20,651 retired, according to registry records as of 1 June 2026.

What is the ICVCM status of this project's methodology?

Methodology assessed by ICVCM and not approved. The CCP label is applied to credits by the registry, issuance by issuance.

Registry data as of June 1, 2026