Azhu Hydro Power Project in Guizhou Province, China

Registry Record

Registry

Verra

Project ID

VCS283

Country

China

Category

Renewable Energy

Methodology

acm0002

Status

Not stated

Credits Issued

552,223 tCO₂e

Credits Retired

268,159 tCO₂e

Data as of

1 June 2026

Issuance and retirement by vintage

Issued Retired
Issuance and retirement by vintageVintages 2008 to 2013: 552,223 tonnes issued and 268,159 retired.0125k250k375k500k2008 issued: 155,163 tonnes2008 retired: 3,877 tonnes20082010 issued: 213,971 tonnes2010 retired: 81,193 tonnes20102011 issued: 53,672 tonnes2011 retired: 53,672 tonnes20112012 issued: 96,959 tonnes2012 retired: 96,959 tonnes20122013 issued: 32,458 tonnes2013 retired: 32,458 tonnes2013
VintageIssued (tCO₂e)Retired (tCO₂e)
201332,45832,458
201296,95996,959
201153,67253,672
2010213,97181,193
2008155,1633,877

Source: Registry records · Data as of 1 June 2026

Credit Passport in detail

ICVCM quality status

Methodology assessed by ICVCM and not approved.

  • Programme: Verified Carbon Standard, CCP-eligible since May 2024.
  • ACM0002 - Grid-connected electricity generation from renewable sources - 1.0-21.0: does not meet the Core Carbon Principles

The CCP label is applied to credits by the registry, issuance by issuance. An approved methodology means credits from this project can be eligible; it does not mean every credit carries the label.

Source: ICVCM assessment decisions · Decisions read 19 September 2026

What this layer checks

CORSIA screen

A screen against published ICAO criteria, not an eligibility determination.

First phase, 2024 to 2026

  • ProgrammePassesVerified Carbon Standard is approved by ICAO for 2024 to 2026.
  • DatesDoes not passCredits were issued for vintage 2008, so crediting began before 1 January 2016.
  • Host country authorisationCannot be confirmed from available dataAuthorisation is granted per activity. This screen cannot confirm whether this project holds a Letter of Authorization.

Second phase, 2027 to 2029

  • ProgrammePassesVerified Carbon Standard is approved by ICAO for 2027 to 2029.
  • DatesDoes not passCredits were issued for vintage 2008, so crediting began before 1 January 2016.

Programme-specific exclusions were not assessed. Host country context is under Article 6 below.

Source: ICAO eligibility decisions and registry records · Criteria verified 25 September 2026

What this layer checks

China and Article 6

Bilateral agreements
0
Authority for the Paris Agreement Crediting Mechanism
Appointed
Participation requirements for the Mechanism
Not published
Cooperative approaches
0
Article 6.2 activities
0
Crediting Mechanism activities approved by the host
0
Crediting Mechanism activities registered
0

This is country-level context. It does not show whether this project is authorised.

Source: UN Article 6 tracking · Data as of 4 September 2026

What this layer checks

Recorded buyers

No organisation named as beneficiary in registry records.

Retired credits from this project? See what a company can still say about them under the EU green claims rules.

Source: Registry records · Data as of 1 June 2026

What this layer checks

Azhu Hydro Power Project in Guizhou Province, China is registered with Verra under the acm0002 protocol, located in China. As of 1 June 2026, registry records show 552,223 tonnes issued and 268,159 tonnes retired. This reflects registry-reported figures, not an independent quality assessment.

Related

Similar projects

Same methodology and country, largest issuance first.

Questions about this project

How many credits has Azhu Hydro Power Project in Guizhou Province, China issued?

552,223 tonnes of credits have been issued and 268,159 retired, according to registry records as of 1 June 2026.

What is the ICVCM status of this project's methodology?

Methodology assessed by ICVCM and not approved. The CCP label is applied to credits by the registry, issuance by issuance.

Registry data as of June 1, 2026