Beijing Guanting Wind Power Project Phase II and Phase II addition

Registry Record

Registry

Verra

Project ID

VCS830

Country

China

Category

Renewable Energy

Methodology

acm0002

Status

Registered

Credits Issued

1,140,275 tCO₂e

Credits Retired

1,119,649 tCO₂e

Data as of

1 June 2026

Issuance and retirement by vintage

Issued Retired
Issuance and retirement by vintageVintages 2011 to 2018: 1,140,275 tonnes issued and 1,119,649 retired.0125k250k375k500k2011 issued: 210,126 tonnes2011 retired: 210,115 tonnes20112012 issued: 74,414 tonnes2012 retired: 74,414 tonnes20122013 issued: 185,233 tonnes2013 retired: 185,166 tonnes20132014 issued: 156,607 tonnes2014 retired: 148,559 tonnes20142015 issued: 130,782 tonnes2015 retired: 124,532 tonnes20152016 issued: 138,075 tonnes2016 retired: 131,825 tonnes20162017 issued: 152,900 tonnes2017 retired: 152,900 tonnes20172018 issued: 92,138 tonnes2018 retired: 92,138 tonnes2018
VintageIssued (tCO₂e)Retired (tCO₂e)
201892,13892,138
2017152,900152,900
2016138,075131,825
2015130,782124,532
2014156,607148,559
2013185,233185,166
201274,41474,414
2011210,126210,115

Source: Registry records · Data as of 1 June 2026

Credit Passport in detail

ICVCM quality status

Methodology assessed by ICVCM and not approved.

  • Programme: Verified Carbon Standard, CCP-eligible since May 2024.
  • ACM0002 - Grid-connected electricity generation from renewable sources - 1.0-21.0: does not meet the Core Carbon Principles

The CCP label is applied to credits by the registry, issuance by issuance. An approved methodology means credits from this project can be eligible; it does not mean every credit carries the label.

Source: ICVCM assessment decisions · Decisions read 19 September 2026

What this layer checks

CORSIA screen

A screen against published ICAO criteria, not an eligibility determination.

First phase, 2024 to 2026

  • ProgrammePassesVerified Carbon Standard is approved by ICAO for 2024 to 2026.
  • DatesDoes not passCredits were issued for vintage 2011, so crediting began before 1 January 2016.
  • Host country authorisationCannot be confirmed from available dataAuthorisation is granted per activity. This screen cannot confirm whether this project holds a Letter of Authorization.

Second phase, 2027 to 2029

  • ProgrammePassesVerified Carbon Standard is approved by ICAO for 2027 to 2029.
  • DatesDoes not passCredits were issued for vintage 2011, so crediting began before 1 January 2016.

Programme-specific exclusions were not assessed. Host country context is under Article 6 below.

Source: ICAO eligibility decisions and registry records · Criteria verified 25 September 2026

What this layer checks

China and Article 6

Bilateral agreements
0
Authority for the Paris Agreement Crediting Mechanism
Appointed
Participation requirements for the Mechanism
Not published
Cooperative approaches
0
Article 6.2 activities
0
Crediting Mechanism activities approved by the host
0
Crediting Mechanism activities registered
0

This is country-level context. It does not show whether this project is authorised.

Source: UN Article 6 tracking · Data as of 4 September 2026

What this layer checks

Recorded buyers

Organisations named in registry retirement records. Many retirements name no beneficiary, so this list is partial.

27.2% of retired tonnes name an organisation as beneficiary.

OrganisationTonnes retiredLatest year
Toucan205,5562021
Yamato Transport92,1382024
Maurice Blackburn6,7952018

Retired credits from this project? See what a company can still say about them under the EU green claims rules.

Source: Registry records · Data as of 1 June 2026

What this layer checks

Beijing Guanting Wind Power Project Phase II and Phase II addition is registered with Verra under the acm0002 protocol, located in China. As of 1 June 2026, registry records show 1,140,275 tonnes issued and 1,119,649 tonnes retired. This reflects registry-reported figures, not an independent quality assessment.

Related

Similar projects

Same methodology and country, largest issuance first.

Questions about this project

How many credits has Beijing Guanting Wind Power Project Phase II and Phase II addition issued?

1,140,275 tonnes of credits have been issued and 1,119,649 retired, according to registry records as of 1 June 2026.

What is the ICVCM status of this project's methodology?

Methodology assessed by ICVCM and not approved. The CCP label is applied to credits by the registry, issuance by issuance.

Which organisations have retired credits from Beijing Guanting Wind Power Project Phase II and Phase II addition?

Registry records name 3 organisations, including Toucan, Yamato Transport, Maurice Blackburn. Many retirements name no beneficiary.

Registry data as of June 1, 2026