Gansu Yumen Diwopu Phase II Wind Power Project

Registry Record

Registry

Verra

Project ID

VCS715

Country

China

Category

Renewable Energy

Methodology

acm0002

Status

Registered

Credits Issued

273,177 tCO₂e

Credits Retired

168,612 tCO₂e

Data as of

1 June 2026

Issuance and retirement by vintage

Issued Retired
Issuance and retirement by vintageVintages 2009 to 2019: 273,177 tonnes issued and 168,612 retired.025k50k75k100k2009 issued: 34,777 tonnes2009 retired: 34,777 tonnes20092010 issued: 67,826 tonnes2010 retired: 67,826 tonnes20102017 issued: 53,409 tonnes2017 retired: 1,000 tonnes20172018 issued: 73,940 tonnes2018 retired: 65,009 tonnes20182019 issued: 43,225 tonnes2019
VintageIssued (tCO₂e)Retired (tCO₂e)
201943,225none
201873,94065,009
201753,4091,000
201067,82667,826
200934,77734,777

Source: Registry records · Data as of 1 June 2026

Credit Passport in detail

ICVCM quality status

Methodology assessed by ICVCM and not approved.

  • Programme: Verified Carbon Standard, CCP-eligible since May 2024.
  • ACM0002 - Grid-connected electricity generation from renewable sources - 1.0-21.0: does not meet the Core Carbon Principles

The CCP label is applied to credits by the registry, issuance by issuance. An approved methodology means credits from this project can be eligible; it does not mean every credit carries the label.

Source: ICVCM assessment decisions · Decisions read 19 September 2026

What this layer checks

CORSIA screen

A screen against published ICAO criteria, not an eligibility determination.

First phase, 2024 to 2026

  • ProgrammePassesVerified Carbon Standard is approved by ICAO for 2024 to 2026.
  • DatesDoes not passCredits were issued for vintage 2009, so crediting began before 1 January 2016.
  • Host country authorisationCannot be confirmed from available dataAuthorisation is granted per activity. This screen cannot confirm whether this project holds a Letter of Authorization.

Second phase, 2027 to 2029

  • ProgrammePassesVerified Carbon Standard is approved by ICAO for 2027 to 2029.
  • DatesDoes not passCredits were issued for vintage 2009, so crediting began before 1 January 2016.

Programme-specific exclusions were not assessed. Host country context is under Article 6 below.

Source: ICAO eligibility decisions and registry records · Criteria verified 25 September 2026

What this layer checks

China and Article 6

Bilateral agreements
0
Authority for the Paris Agreement Crediting Mechanism
Appointed
Participation requirements for the Mechanism
Not published
Cooperative approaches
0
Article 6.2 activities
0
Crediting Mechanism activities approved by the host
0
Crediting Mechanism activities registered
0

This is country-level context. It does not show whether this project is authorised.

Source: UN Article 6 tracking · Data as of 4 September 2026

What this layer checks

Recorded buyers

No organisation named as beneficiary in registry records.

Retired credits from this project? See what a company can still say about them under the EU green claims rules.

Source: Registry records · Data as of 1 June 2026

What this layer checks

Gansu Yumen Diwopu Phase II Wind Power Project is registered with Verra under the acm0002 protocol, located in China. As of 1 June 2026, registry records show 273,177 tonnes issued and 168,612 tonnes retired. This reflects registry-reported figures, not an independent quality assessment.

Related

Similar projects

Same methodology and country, largest issuance first.

Questions about this project

How many credits has Gansu Yumen Diwopu Phase II Wind Power Project issued?

273,177 tonnes of credits have been issued and 168,612 retired, according to registry records as of 1 June 2026.

What is the ICVCM status of this project's methodology?

Methodology assessed by ICVCM and not approved. The CCP label is applied to credits by the registry, issuance by issuance.

Registry data as of June 1, 2026