Lican Hydroelectric Plant

Registry Record

Registry

Verra

Project ID

VCS1083

Country

Chile

Category

Renewable Energy

Methodology

am0026

Status

Registered

Credits Issued

87,914 tCO₂e

Credits Retired

48,091 tCO₂e

Data as of

1 June 2026

Issuance and retirement by vintage

Issued Retired
Issuance and retirement by vintageVintages 2019 to 2021: 87,914 tonnes issued and 48,091 retired.012.5k25k37.5k50k2019 issued: 39,823 tonnes20192020 issued: 38,548 tonnes2020 retired: 38,548 tonnes20202021 issued: 9,543 tonnes2021 retired: 9,543 tonnes2021
VintageIssued (tCO₂e)Retired (tCO₂e)
20219,5439,543
202038,54838,548
201939,823none

Source: Registry records · Data as of 1 June 2026

Credit Passport in detail

ICVCM quality status

No ICVCM decision on this methodology yet.

  • Programme: Verified Carbon Standard, CCP-eligible since May 2024.

The CCP label is applied to credits by the registry, issuance by issuance. An approved methodology means credits from this project can be eligible; it does not mean every credit carries the label.

Source: ICVCM assessment decisions · Decisions read 19 September 2026

What this layer checks

CORSIA screen

A screen against published ICAO criteria, not an eligibility determination.

First phase, 2024 to 2026

  • ProgrammePassesVerified Carbon Standard is approved by ICAO for 2024 to 2026.
  • DatesCannot be confirmed from available dataCredits issued for vintage 2021. The start of the first crediting period is not in registry data.
  • Host country authorisationCannot be confirmed from available dataAuthorisation is granted per activity. This screen cannot confirm whether this project holds a Letter of Authorization.

Second phase, 2027 to 2029

  • ProgrammePassesVerified Carbon Standard is approved by ICAO for 2027 to 2029.
  • DatesCannot be confirmed from available dataCredits issued for vintage 2021. The start of the first crediting period is not in registry data.

Programme-specific exclusions were not assessed. Host country context is under Article 6 below.

Source: ICAO eligibility decisions and registry records · Criteria verified 25 September 2026

What this layer checks

Chile and Article 6

Bilateral agreements
3
Authority for the Paris Agreement Crediting Mechanism
Appointed
Participation requirements for the Mechanism
Published
Cooperative approaches
1
Article 6.2 activities
14
Crediting Mechanism activities approved by the host
30
Crediting Mechanism activities registered
0

This is country-level context. It does not show whether this project is authorised.

Source: UN Article 6 tracking · Data as of 4 September 2026

What this layer checks

Recorded buyers

No organisation named as beneficiary in registry records.

Retired credits from this project? See what a company can still say about them under the EU green claims rules.

Source: Registry records · Data as of 1 June 2026

What this layer checks

Lican Hydroelectric Plant is registered with Verra under the am0026 protocol, located in Chile. As of 1 June 2026, registry records show 87,914 tonnes issued and 48,091 tonnes retired. This reflects registry-reported figures, not an independent quality assessment.

Related

Similar projects

Same methodology and country, largest issuance first.

Questions about this project

How many credits has Lican Hydroelectric Plant issued?

87,914 tonnes of credits have been issued and 48,091 retired, according to registry records as of 1 June 2026.

What is the ICVCM status of this project's methodology?

No ICVCM decision on this methodology yet. The CCP label is applied to credits by the registry, issuance by issuance.

Registry data as of June 1, 2026