Shenyang Laohuchong LFG Power Generation Project

Registry Record

Registry

Verra

Project ID

VCS616

Country

China

Category

GHG Management

Methodology

acm0001, acm0002

Status

Not stated

Credits Issued

55,861 tCO₂e

Credits Retired

None retired yet

Data as of

1 June 2026

Issuance and retirement by vintage

Issued Retired
Issuance and retirement by vintageVintages 2008: 55,861 tonnes issued and 0 retired.025k50k75k100k2008 issued: 55,861 tonnes2008
VintageIssued (tCO₂e)Retired (tCO₂e)
200855,861none

Source: Registry records · Data as of 1 June 2026

Credit Passport in detail

ICVCM quality status

The methodologies this project lists have different ICVCM outcomes, one or more of them approved.

  • Programme: Verified Carbon Standard, CCP-eligible since May 2024.
  • This project lists 2 methodologies; 2 of them appear in ICVCM's assessment table.
  • ACM0001 - Flaring or use of landfill gas - 15.0-19.0: approved
  • ACM0001 - Flaring or use of landfill gas - 19.0: under assessment
  • ACM0002 - Grid-connected electricity generation from renewable sources - 1.0-21.0: does not meet the Core Carbon Principles

The CCP label is applied to credits by the registry, issuance by issuance. An approved methodology means credits from this project can be eligible; it does not mean every credit carries the label.

Source: ICVCM assessment decisions · Decisions read 19 September 2026

What this layer checks

CORSIA screen

A screen against published ICAO criteria, not an eligibility determination.

First phase, 2024 to 2026

  • ProgrammePassesVerified Carbon Standard is approved by ICAO for 2024 to 2026.
  • DatesDoes not passCredits were issued for vintage 2008, so crediting began before 1 January 2016.
  • Host country authorisationCannot be confirmed from available dataAuthorisation is granted per activity. This screen cannot confirm whether this project holds a Letter of Authorization.

Second phase, 2027 to 2029

  • ProgrammePassesVerified Carbon Standard is approved by ICAO for 2027 to 2029.
  • DatesDoes not passCredits were issued for vintage 2008, so crediting began before 1 January 2016.

Programme-specific exclusions were not assessed. Host country context is under Article 6 below.

Source: ICAO eligibility decisions and registry records · Criteria verified 25 September 2026

What this layer checks

China and Article 6

Bilateral agreements
0
Authority for the Paris Agreement Crediting Mechanism
Appointed
Participation requirements for the Mechanism
Not published
Cooperative approaches
0
Article 6.2 activities
0
Crediting Mechanism activities approved by the host
0
Crediting Mechanism activities registered
0

This is country-level context. It does not show whether this project is authorised.

Source: UN Article 6 tracking · Data as of 4 September 2026

What this layer checks

Recorded buyers

No retirements in registry records.

Retired credits from this project? See what a company can still say about them under the EU green claims rules.

Source: Registry records · Data as of 1 June 2026

What this layer checks

Shenyang Laohuchong LFG Power Generation Project is registered with Verra under the acm0001, acm0002 protocol, located in China. As of 1 June 2026, registry records show 55,861 tonnes issued and none retired to date. This reflects registry-reported figures, not an independent quality assessment.

Related

Similar projects

Same methodology and country, largest issuance first.

Questions about this project

How many credits has Shenyang Laohuchong LFG Power Generation Project issued?

55,861 tonnes of credits have been issued and 0 retired, according to registry records as of 1 June 2026.

What is the ICVCM status of this project's methodology?

The methodologies this project lists have different ICVCM outcomes, one or more of them approved. The CCP label is applied to credits by the registry, issuance by issuance.

Registry data as of June 1, 2026