Sichuan Furong Coal Mine Methane Utilization Project
Registry
Verra
Project ID
VCS1446
Country
Category
GHG Management
Methodology
Status
Registered
Credits Issued
2,792,506 tCO₂e
Credits Retired
1,453,846 tCO₂e
Data as of
1 June 2026
Credit Passport
How to read itIssuance and retirement by vintage
| Vintage | Issued (tCO₂e) | Retired (tCO₂e) |
|---|---|---|
| 2020 | 91,177 | 30,000 |
| 2019 | 367,894 | 33,496 |
| 2018 | 382,173 | 20,250 |
| 2017 | 352,876 | 352,876 |
| 2016 | 345,337 | 24,650 |
| 2015 | 298,207 | 105,256 |
| 2014 | 290,254 | 278,384 |
| 2013 | 230,209 | 180,154 |
| 2012 | 155,766 | 150,270 |
| 2011 | 164,936 | 164,934 |
| 2010 | 113,677 | 113,576 |
Source: Registry records · Data as of 1 June 2026
Credit Passport in detail
ICVCM quality status
ICVCM approved some versions of this methodology and not others. The version this project uses is not in registry data.
- Programme: Verified Carbon Standard, CCP-eligible since May 2024.
- ACM0008 - Abatement of methane from coal mines - 6.0-8.0: approved
- ACM0008 - Abatement of methane from coal mines - 8.0: under assessment
The CCP label is applied to credits by the registry, issuance by issuance. An approved methodology means credits from this project can be eligible; it does not mean every credit carries the label.
Source: ICVCM assessment decisions · Decisions read 19 September 2026
CORSIA screen
A screen against published ICAO criteria, not an eligibility determination.
First phase, 2024 to 2026
- ProgrammePassesVerified Carbon Standard is approved by ICAO for 2024 to 2026.
- DatesDoes not passCredits were issued for vintage 2010, so crediting began before 1 January 2016.
- Host country authorisationCannot be confirmed from available dataAuthorisation is granted per activity. This screen cannot confirm whether this project holds a Letter of Authorization.
Second phase, 2027 to 2029
- ProgrammePassesVerified Carbon Standard is approved by ICAO for 2027 to 2029.
- DatesDoes not passCredits were issued for vintage 2010, so crediting began before 1 January 2016.
Programme-specific exclusions were not assessed. Host country context is under Article 6 below.
Source: ICAO eligibility decisions and registry records · Criteria verified 25 September 2026
China and Article 6
- Bilateral agreements
- 0
- Authority for the Paris Agreement Crediting Mechanism
- Appointed
- Participation requirements for the Mechanism
- Not published
- Cooperative approaches
- 0
- Article 6.2 activities
- 0
- Crediting Mechanism activities approved by the host
- 0
- Crediting Mechanism activities registered
- 0
This is country-level context. It does not show whether this project is authorised.
Source: UN Article 6 tracking · Data as of 4 September 2026
Recorded buyers
No organisation named as beneficiary in registry records.
Retired credits from this project? See what a company can still say about them under the EU green claims rules.
Source: Registry records · Data as of 1 June 2026
Sichuan Furong Coal Mine Methane Utilization Project is registered with Verra under the acm0008 protocol, located in China. As of 1 June 2026, registry records show 2,792,506 tonnes issued and 1,453,846 tonnes retired. This reflects registry-reported figures, not an independent quality assessment.
Related
Similar projects
- Guizhou Panjiang Low Concentration Coal Mine Methane Power Generation Project Phase 3 1,346,326 t issued
- Huineng Low Concentration Coal Mine Methane Utilization Project 1,278,355 t issued
- Guizhou Panjiang Low Concentration Coal Mine Methane Power Generation Project Phase 2 1,111,716 t issued
- Tiefa Coal Industry Group CMM Utilization Project 951,662 t issued
- Liyang 15 MW Low-concentration CMM Power Generation Project 757,901 t issued
Same methodology and country, largest issuance first.
Questions about this project
How many credits has Sichuan Furong Coal Mine Methane Utilization Project issued?
2,792,506 tonnes of credits have been issued and 1,453,846 retired, according to registry records as of 1 June 2026.
What is the ICVCM status of this project's methodology?
ICVCM approved some versions of this methodology and not others. The version this project uses is not in registry data. The CCP label is applied to credits by the registry, issuance by issuance.
Registry data as of June 1, 2026