Einheitliche Anlage Stahlwerk Saarstahl AG
Einheitliche Anlage Stahlwerk Saarstahl AG is a production of pig iron or steel installation in Germany. In 2025 it reported 161,995 tonnes of verified emissions against 1,211 free allowances.
Key figures
Country
Activity
Installation ID
DE 59
Verified emissions, 2025
161,995 tCO₂e
Free allocation, 2025
1,211 allowances
Allowance position, 2025
160,784 short
Compliance, 2024
A
Permit
14220-0023
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 161,995 | 1,211 | 160,784 short |
| 2024 | 231,860 | 2,030 | 229,830 short |
| 2023 | 164,617 | 3,632 | 160,985 short |
| 2022 | 216,664 | 3,365 | 213,299 short |
| 2021 | 279,476 | 2,986 | 276,490 short |
| 2020 | 185,920 | 7,394 | 178,526 short |
| 2019 | 218,828 | 7,550 | 211,278 short |
| 2018 | 277,265 | 7,705 | 269,560 short |
| 2017 | 246,105 | 7,858 | 238,247 short |
| 2016 | 187,511 | 8,010 | 179,501 short |
| 2015 | 197,491 | 8,160 | 189,331 short |
| 2014 | 197,677 | 8,309 | 189,368 short |
| 2013 | 177,692 | 8,352 | 169,340 short |
Verified emissions changed by -8.8% from 2013 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
In 2025, verified emissions exceeded free allocation by 160,784 allowances, which the operator had to obtain.
Illustrative value at the latest reference price of €85.90 (28 September 2026): €13,811,346. Not the installation's actual cost, which depends on when and how it acquired allowances.
Price source: EU ETS primary auctions · latest price
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
CBAM context
This activity falls in the iron and steel sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.
| 2026 | 2027 | 2028 | 2029 | 2030 | 2031 | 2032 | 2033 | 2034 |
|---|---|---|---|---|---|---|---|---|
| 97.5% | 95% | 90% | 77.5% | 51.5% | 39% | 26.5% | 14% | 0% |
Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.
Proposed change
A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.
More on CBAM: the India CBAM Center and what CBAM is and how it works.
Nearby installations
Production of pig iron or steel installations in Germany, largest first.
- Integriertes Hüttenwerk Duisburg 6,705,307 t in 2025
- Glocke Duisburg 3,901,188 t in 2025
- Roheisenerzeugung Dillingen 3,646,506 t in 2025
- Glocke Salzgitter 3,497,812 t in 2025
- Einheitliche Anlage Bremen 2,170,849 t in 2025
Questions about Einheitliche Anlage Stahlwerk Saarstahl AG
How much did Einheitliche Anlage Stahlwerk Saarstahl AG emit in 2025?
161,995 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did Einheitliche Anlage Stahlwerk Saarstahl AG receive?
1,211 in 2025.
Did Einheitliche Anlage Stahlwerk Saarstahl AG surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.