Energiezentrale Spanplattenwerk 2 und 3
Energiezentrale Spanplattenwerk 2 und 3 is a combustion of fuels installation in Germany. In 2025 it reported 16,897 tonnes of verified emissions against 43,276 free allowances.
Key figures
Country
Activity
Installation ID
DE 202818
Verified emissions, 2025
16,897 tCO₂e
Free allocation, 2025
43,276 allowances
Allowance position, 2025
26,379 surplus
Compliance, 2024
A
Permit
14310-1647
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 16,897 | 43,276 | 26,379 surplus |
| 2024 | 19,024 | 44,515 | 25,491 surplus |
| 2023 | 18,151 | 45,754 | 27,603 surplus |
| 2022 | 21,659 | 46,994 | 25,335 surplus |
| 2021 | 20,231 | 48,233 | 28,002 surplus |
| 2020 | 19,416 | 21,938 | 2,522 surplus |
| 2019 | 21,036 | 27,697 | 6,661 surplus |
| 2018 | 22,551 | 33,670 | 11,119 surplus |
| 2017 | 20,804 | 39,843 | 19,039 surplus |
| 2016 | 20,038 | 46,224 | 26,186 surplus |
| 2015 | 21,933 | 52,810 | 30,877 surplus |
| 2014 | 19,168 | 81,817 | 62,649 surplus |
| 2013 | 25,535 | 83,265 | 57,730 surplus |
Verified emissions changed by -33.8% from 2013 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
Free allocation exceeded verified emissions in 2025, by 26,379 allowances.
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
Nearby installations
Combustion of fuels installations in Germany, largest first.
- Kraftwerk Neurath 12,074,600 t in 2025
- Kraftwerk Niederaußem 11,356,402 t in 2025
- Kraftwerk Jänschwalde 9,631,288 t in 2025
- Kraftwerk Schwarze Pumpe 8,715,923 t in 2025
- Kraftwerk Weisweiler 8,312,179 t in 2025
Questions about Energiezentrale Spanplattenwerk 2 und 3
How much did Energiezentrale Spanplattenwerk 2 und 3 emit in 2025?
16,897 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did Energiezentrale Spanplattenwerk 2 und 3 receive?
43,276 in 2025.
Did Energiezentrale Spanplattenwerk 2 und 3 surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.