Faserplattenwerk Satteldorf
Faserplattenwerk Satteldorf is a production or processing of gypsum or plasterboard installation in Germany. In 2025 it reported 14,693 tonnes of verified emissions against 0 free allowances.
Key figures
Country
Installation ID
DE 224290
Verified emissions, 2025
14,693 tCO₂e
Free allocation, 2025
None
Allowance position, 2025
14,693 short
Compliance, 2024
C
Permit
14642-0032
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 14,693 | none | 14,693 short |
| 2024 | 13,315 | none | 13,315 short |
Verified emissions changed by +10.3% from 2024 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
In 2025, verified emissions exceeded free allocation by 14,693 allowances, which the operator had to obtain.
Illustrative value at the latest reference price of €85.90 (28 September 2026): €1,262,129. Not the installation's actual cost, which depends on when and how it acquired allowances.
Price source: EU ETS primary auctions · latest price
Compliance status for 2024: C. Verified emissions for preceding years were not entered by 30 September 2025.
Nearby installations
Production or processing of gypsum or plasterboard installations in Germany, largest first.
- Iphofen Werk I 61,546 t in 2025
- Werk Berlin-Brieselang 36,529 t in 2025
- Gipsbauplattenwerk Schwarze Pumpe 29,146 t in 2025
- Knauf Deutsche Gipswerke KG Rottleberode 26,622 t in 2025
- Knauf Gips KG Neuss 21,219 t in 2025
Questions about Faserplattenwerk Satteldorf
How much did Faserplattenwerk Satteldorf emit in 2025?
14,693 tonnes of verified emissions, per EU Union Registry compliance data.
Did Faserplattenwerk Satteldorf surrender enough allowances?
Its compliance status for 2024 is recorded as "C": Verified emissions for preceding years were not entered by 30 September 2025.