Feuerverzinkung 1 is a production or processing of ferrous metals installation in Germany. In 2025 it reported 23,442 tonnes of verified emissions against 16,322 free allowances.
Key figures
Country
Installation ID
DE 2397
Verified emissions, 2025
23,442 tCO₂e
Free allocation, 2025
16,322 allowances
Allowance position, 2025
7,120 short
Compliance, 2024
A
Permit
14225-0008
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 23,442 | 16,322 | 7,120 short |
| 2024 | 22,012 | 16,931 | 5,081 short |
| 2023 | 21,304 | 20,608 | 696 short |
| 2022 | 23,656 | 20,608 | 3,048 short |
| 2021 | 25,266 | 20,608 | 4,658 short |
| 2020 | 24,375 | 23,617 | 758 short |
| 2019 | 27,228 | 24,115 | 3,113 short |
| 2018 | 27,248 | 24,610 | 2,638 short |
| 2017 | 28,800 | 25,100 | 3,700 short |
| 2016 | 26,562 | 25,584 | 978 short |
| 2015 | 26,443 | 26,064 | 379 short |
| 2014 | 25,474 | 26,538 | 1,064 surplus |
| 2013 | 22,457 | 27,008 | 4,551 surplus |
Verified emissions changed by +4.4% from 2013 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
In 2025, verified emissions exceeded free allocation by 7,120 allowances, which the operator had to obtain.
Illustrative value at the latest reference price of €85.90 (28 September 2026): €611,608. Not the installation's actual cost, which depends on when and how it acquired allowances.
Price source: EU ETS primary auctions · latest price
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
CBAM context
This activity falls in the iron and steel sector of the Carbon Border Adjustment Mechanism. Free allocation for products covered by the Carbon Border Adjustment Mechanism is being reduced each year under current EU law.
| 2026 | 2027 | 2028 | 2029 | 2030 | 2031 | 2032 | 2033 | 2034 |
|---|---|---|---|---|---|---|---|---|
| 97.5% | 95% | 90% | 77.5% | 51.5% | 39% | 26.5% | 14% | 0% |
Share of free allocation remaining for CBAM-covered products, under Directive (EU) 2023/959, Article 10a. It applies to the benchmarks for those products, not necessarily to an installation's whole allocation, so it is not applied to the figures on this page.
Proposed change
A European Commission proposal of 17 July 2026 would restore 15% of the phased-out free allocation for CBAM sectors from 2028 and extend the end of the phase-out from 2034 to 2038. This is a proposal and not yet law.
More on CBAM: the India CBAM Center and what CBAM is and how it works.
Nearby installations
Production or processing of ferrous metals installations in Germany, largest first.
- Wärmöfen Warmbreitbandwalzwerk 285,316 t in 2025
- Fritz Winter Eisengießerei GmbH & Co. KG 140,453 t in 2025
- Reduktionsanlage 112,670 t in 2025
- Warmwalzwerk 112,381 t in 2025
- Eisenwerk Brühl GmbH 111,695 t in 2025
Questions about Feuerverzinkung 1
How much did Feuerverzinkung 1 emit in 2025?
23,442 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did Feuerverzinkung 1 receive?
16,322 in 2025.
Did Feuerverzinkung 1 surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.