FHW 107
FHW 107 is a combustion of fuels installation in Germany. In 2025 it reported 7,105 tonnes of verified emissions against 1,779 free allowances.
Key figures
Country
Activity
Installation ID
DE 768
Verified emissions, 2025
7,105 tCO₂e
Free allocation, 2025
1,779 allowances
Allowance position, 2025
5,326 short
Compliance, 2024
A
Permit
14310-0162
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 7,105 | 1,779 | 5,326 short |
| 2024 | 8,510 | 1,830 | 6,680 short |
| 2023 | 9,993 | 1,881 | 8,112 short |
| 2022 | 8,795 | 1,932 | 6,863 short |
| 2021 | 9,791 | 1,983 | 7,808 short |
| 2020 | 8,032 | 2,926 | 5,106 short |
| 2019 | 9,194 | 3,694 | 5,500 short |
| 2018 | 8,024 | 4,491 | 3,533 short |
| 2017 | 8,940 | 5,313 | 3,627 short |
| 2016 | 9,069 | 6,164 | 2,905 short |
| 2015 | 8,130 | 7,043 | 1,087 short |
| 2014 | 7,511 | 7,949 | 438 surplus |
| 2013 | 9,296 | 8,882 | 414 short |
Verified emissions changed by -23.6% from 2013 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
In 2025, verified emissions exceeded free allocation by 5,326 allowances, which the operator had to obtain.
Illustrative value at the latest reference price of €85.90 (28 September 2026): €457,503. Not the installation's actual cost, which depends on when and how it acquired allowances.
Price source: EU ETS primary auctions · latest price
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
Nearby installations
Combustion of fuels installations in Germany, largest first.
- Kraftwerk Neurath 12,074,600 t in 2025
- Kraftwerk Niederaußem 11,356,402 t in 2025
- Kraftwerk Jänschwalde 9,631,288 t in 2025
- Kraftwerk Schwarze Pumpe 8,715,923 t in 2025
- Kraftwerk Weisweiler 8,312,179 t in 2025
Questions about FHW 107
How much did FHW 107 emit in 2025?
7,105 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did FHW 107 receive?
1,779 in 2025.
Did FHW 107 surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.