Gaskraftwerk Emden
Gaskraftwerk Emden is a combustion of fuels installation in Germany. In 2025 it reported 568 tonnes of verified emissions against 0 free allowances.
Key figures
Country
Activity
Installation ID
DE 1000
Verified emissions, 2025
568 tCO₂e
Free allocation, 2025
None
Allowance position, 2025
568 short
Compliance, 2024
A
Permit
14310-0425
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 568 | none | 568 short |
| 2024 | 753 | none | 753 short |
| 2023 | 369 | none | 369 short |
| 2022 | 83 | none | 83 short |
| 2021 | 363 | none | 363 short |
| 2020 | 1,185 | none | 1,185 short |
| 2019 | 862 | none | 862 short |
| 2018 | 268 | none | 268 short |
| 2017 | 267 | none | 267 short |
| 2016 | 115 | none | 115 short |
| 2015 | 798 | none | 798 short |
| 2014 | 852 | none | 852 short |
| 2013 | 262 | none | 262 short |
Verified emissions changed by +116.8% from 2013 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
In 2025, verified emissions exceeded free allocation by 568 allowances, which the operator had to obtain.
Illustrative value at the latest reference price of €84.70 (1 October 2026): €48,110. Not the installation's actual cost, which depends on when and how it acquired allowances.
Price source: EU ETS primary auctions · latest price
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
Nearby installations
Combustion of fuels installations in Germany, largest first.
- Kraftwerk Neurath 12,074,600 t in 2025
- Kraftwerk Niederaußem 11,356,402 t in 2025
- Kraftwerk Jänschwalde 9,631,288 t in 2025
- Kraftwerk Schwarze Pumpe 8,715,923 t in 2025
- Kraftwerk Weisweiler 8,312,179 t in 2025
Questions about Gaskraftwerk Emden
How much did Gaskraftwerk Emden emit in 2025?
568 tonnes of verified emissions, per EU Union Registry compliance data.
Did Gaskraftwerk Emden surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.