Heizkraftwerk Adlerstraße
Heizkraftwerk Adlerstraße is a combustion of fuels installation in Germany. In 2025 it reported 5,744 tonnes of verified emissions against 1,161 free allowances.
Key figures
Country
Activity
Installation ID
DE 210532
Verified emissions, 2025
5,744 tCO₂e
Free allocation, 2025
1,161 allowances
Allowance position, 2025
4,583 short
Compliance, 2024
A
Permit
14310-1933
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 5,744 | 1,161 | 4,583 short |
| 2024 | 9,134 | 1,194 | 7,940 short |
| 2023 | 3,028 | 1,227 | 1,801 short |
| 2022 | 1,948 | 1,260 | 688 short |
| 2021 | 1,421 | 1,294 | 127 short |
| 2020 | 1,220 | 1,868 | 648 surplus |
| 2019 | 1,433 | 2,360 | 927 surplus |
| 2018 | 437 | 473 | 36 surplus |
Verified emissions changed by +1,214.4% from 2018 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
In 2025, verified emissions exceeded free allocation by 4,583 allowances, which the operator had to obtain.
Illustrative value at the latest reference price of €85.90 (28 September 2026): €393,680. Not the installation's actual cost, which depends on when and how it acquired allowances.
Price source: EU ETS primary auctions · latest price
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
Nearby installations
Combustion of fuels installations in Germany, largest first.
- Kraftwerk Neurath 12,074,600 t in 2025
- Kraftwerk Niederaußem 11,356,402 t in 2025
- Kraftwerk Jänschwalde 9,631,288 t in 2025
- Kraftwerk Schwarze Pumpe 8,715,923 t in 2025
- Kraftwerk Weisweiler 8,312,179 t in 2025
Questions about Heizkraftwerk Adlerstraße
How much did Heizkraftwerk Adlerstraße emit in 2025?
5,744 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did Heizkraftwerk Adlerstraße receive?
1,161 in 2025.
Did Heizkraftwerk Adlerstraße surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.