Heizwerk 2 Flugplatz Ramstein-Miesenbach
Heizwerk 2 Flugplatz Ramstein-Miesenbach is a combustion of fuels installation in Germany. In 2025 it reported 4 tonnes of verified emissions against 54 free allowances.
Key figures
Country
Activity
Installation ID
DE 1036
Verified emissions, 2025
4 tCO₂e
Free allocation, 2025
54 allowances
Allowance position, 2025
50 surplus
Compliance, 2024
A
Permit
14310-0464
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 4 | 54 | 50 surplus |
| 2024 | 41 | 54 | 13 surplus |
| 2023 | 29 | 54 | 25 surplus |
| 2022 | 10 | 54 | 44 surplus |
| 2021 | 12 | 54 | 42 surplus |
| 2020 | 35 | 0 | 35 short |
| 2019 | 24 | 0 | 24 short |
| 2018 | 326 | 0 | 326 short |
| 2017 | 712 | 0 | 712 short |
| 2016 | 432 | 0 | 432 short |
| 2015 | 13 | 0 | 13 short |
| 2014 | 33 | 0 | 33 short |
| 2013 | 189 | 1,079 | 890 surplus |
Verified emissions changed by -97.9% from 2013 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
Free allocation exceeded verified emissions in 2025, by 50 allowances.
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
Nearby installations
Combustion of fuels installations in Germany, largest first.
- Kraftwerk Neurath 12,074,600 t in 2025
- Kraftwerk Niederaußem 11,356,402 t in 2025
- Kraftwerk Jänschwalde 9,631,288 t in 2025
- Kraftwerk Schwarze Pumpe 8,715,923 t in 2025
- Kraftwerk Weisweiler 8,312,179 t in 2025
Questions about Heizwerk 2 Flugplatz Ramstein-Miesenbach
How much did Heizwerk 2 Flugplatz Ramstein-Miesenbach emit in 2025?
4 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did Heizwerk 2 Flugplatz Ramstein-Miesenbach receive?
54 in 2025.
Did Heizwerk 2 Flugplatz Ramstein-Miesenbach surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.