Heizwerk Essen Nord
Heizwerk Essen Nord is a combustion of fuels installation in Germany. In 2025 it reported 1,612 tonnes of verified emissions against 145 free allowances.
Key figures
Country
Activity
Installation ID
DE 1266
Verified emissions, 2025
1,612 tCO₂e
Free allocation, 2025
145 allowances
Allowance position, 2025
1,467 short
Compliance, 2024
A
Permit
14310-0711
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 1,612 | 145 | 1,467 short |
| 2024 | 1,248 | 282 | 966 short |
| 2023 | 326 | 282 | 44 short |
| 2022 | 2,569 | 65 | 2,504 short |
| 2021 | 651 | 65 | 586 short |
| 2020 | 128 | 90 | 38 short |
| 2019 | 302 | 226 | 76 short |
| 2018 | 942 | 0 | 942 short |
| 2017 | 288 | 0 | 288 short |
| 2016 | 461 | 0 | 461 short |
| 2015 | 120 | 0 | 120 short |
| 2014 | 68 | 973 | 905 surplus |
| 2013 | 1,493 | 1,087 | 406 short |
Verified emissions changed by +8% from 2013 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
In 2025, verified emissions exceeded free allocation by 1,467 allowances, which the operator had to obtain.
Illustrative value at the latest reference price of €84.87 (29 September 2026): €124,504. Not the installation's actual cost, which depends on when and how it acquired allowances.
Price source: EU ETS primary auctions · latest price
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
Nearby installations
Combustion of fuels installations in Germany, largest first.
- Kraftwerk Neurath 12,074,600 t in 2025
- Kraftwerk Niederaußem 11,356,402 t in 2025
- Kraftwerk Jänschwalde 9,631,288 t in 2025
- Kraftwerk Schwarze Pumpe 8,715,923 t in 2025
- Kraftwerk Weisweiler 8,312,179 t in 2025
Questions about Heizwerk Essen Nord
How much did Heizwerk Essen Nord emit in 2025?
1,612 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did Heizwerk Essen Nord receive?
145 in 2025.
Did Heizwerk Essen Nord surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.