Motorenprüfstand Werk 1
Motorenprüfstand Werk 1 is a combustion of fuels installation in Germany. In 2025 it reported 5,995 tonnes of verified emissions against 753 free allowances.
Key figures
Country
Activity
Installation ID
DE 204641
Verified emissions, 2025
5,995 tCO₂e
Free allocation, 2025
753 allowances
Allowance position, 2025
5,242 short
Compliance, 2024
A
Permit
14310-1820
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 5,995 | 753 | 5,242 short |
| 2024 | 5,639 | 953 | 4,686 short |
| 2023 | 5,466 | 953 | 4,513 short |
| 2022 | 7,007 | 953 | 6,054 short |
| 2021 | 6,166 | 1,180 | 4,986 short |
| 2020 | 7,493 | 5,031 | 2,462 short |
| 2019 | 8,621 | 5,137 | 3,484 short |
| 2018 | 7,531 | 12,967 | 5,436 surplus |
| 2017 | 10,070 | 13,225 | 3,155 surplus |
| 2016 | 11,756 | 13,480 | 1,724 surplus |
| 2015 | 13,452 | 13,733 | 281 surplus |
| 2014 | 16,443 | 13,983 | 2,460 short |
| 2013 | 16,854 | 14,230 | 2,624 short |
Verified emissions changed by -64.4% from 2013 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
In 2025, verified emissions exceeded free allocation by 5,242 allowances, which the operator had to obtain.
Illustrative value at the latest reference price of €85.90 (28 September 2026): €450,288. Not the installation's actual cost, which depends on when and how it acquired allowances.
Price source: EU ETS primary auctions · latest price
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
Nearby installations
Combustion of fuels installations in Germany, largest first.
- Kraftwerk Neurath 12,074,600 t in 2025
- Kraftwerk Niederaußem 11,356,402 t in 2025
- Kraftwerk Jänschwalde 9,631,288 t in 2025
- Kraftwerk Schwarze Pumpe 8,715,923 t in 2025
- Kraftwerk Weisweiler 8,312,179 t in 2025
Questions about Motorenprüfstand Werk 1
How much did Motorenprüfstand Werk 1 emit in 2025?
5,995 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did Motorenprüfstand Werk 1 receive?
753 in 2025.
Did Motorenprüfstand Werk 1 surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.